Mobilization (Unit Bid Amount May Not Exceed 5% of Subtotal) Contract Totals Date: 03/31/16 Arkansas State Highway and Transportation Department Page: 1 Bid Tabulation Summary Bids Opened for Job 030443 Letting Date: 03/23/16 STPR-0VLY(117) County: Howard Job Name: Hwys. 371 & 980 (Sel. Secs.) (Mill & Inlay) (S) Length: 7.660 Miles Routes: 371 & 980 Total % over Rank Vendor No./Name Bid Low Bid 1 REDS10 Redstone Const. Group, Inc. $ 1,718,696.23 100.0000% 2 HALL25 R. K. Hall, LLC $ 1,913,385.55 111.3277%
One winning bid
Single 1 winning bid$800,000per contract
- Letting
- Mar 23, 2016
- Quantity
- 1 L.S.
- Agency
- ARDOT
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 1 winning bids behind that median, with the agency’s own document one click away.
- Agency
- ARDOT · Little River Sevier, Arkansas
- Letting
- Mar 23, 2016
- Quantity
- 1 L.S.
- Contractor
- Jensen Construction CO.
- Winning price
- $800,000 / LS
What’s behind $800,000
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 1 bids charted, so you can see clusters and outliers.
1 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Who let the work, and how agencies and states compare
EstimatorThe median split by developer, city and state DOT, a per-agency comparison where the counts carry it, and the median by state and county for this item.
See what Estimator addsRelated items
Other paving items priced per LS, ranked by how much evidence each has.
- Precast Reinf. Conc. Three Sided Structure NO. 1$141,57532 bids
- Precast Reinf. Conc. Three Sided Structure NO. 2$195,00010 bids
- Concrete Pavement Joint Layout 03.$1,0765 bids
- Precast Reinf. Conc. Three Sided Structure NO. 3$136,5004 bids
- Clearing and Grubbing (Maximum Allowable Bid $ 10,000.00 per Hectare)(Approximately 2 Removing Concrete Driveway$20,0003 bids
- Coating Concrete Surfaces (At MP 126.100 (Bin 014156))$35,7443 bids
- Mobilization Concrete Driveway, 150 Mm Thick (Includes Wire Mesh)$35,0003 bids
- NS Contract Aggr. & Select Matl. Quality Control Aggr. & Select Matl. Quality Control$24,0003 bids
1 observation
1 agency in 1 state · lettings Mar 23, 2016
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|