Construction Staking Electrical
Median winning unit price
Deep 372 winning bids≈$2,090/ EALow confidence
- Winning bids
- 372
- Source documents
- 45
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 372 winning bids behind that median, with the agency’s own document one click away.
- Agency
- WisDOT · Milwaukee, Wisconsin
- Letting
- Feb 10, 2026
- Quantity
- 1 EACH
- Contractor
- Lalonde Contractors Incorporated
- Winning price
- $1,900 / EA
Median by quarter
EstimatorHow this item has priced over time, quarter by quarter, from the same rows as the headline figure.
See what Estimator addsWhat’s behind $2,090
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 372 bids charted, so you can see clusters and outliers.
372 observations
Agency, county, letting date, quantity and the price as printed.
45 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Who let the work, and how agencies and states compare
EstimatorThe median split by developer, city and state DOT, a per-agency comparison where the counts carry it, and the median by state and county for this item.
See what Estimator addsRelated items
Other street lighting items priced per EA, ranked by how much evidence each has.
- Electrical Service Meter Breaker$1,850546 bids
- Electrical Service Connection$2,500246 bids
- Electrical Service SE-5$3,825207 bids
- Electrical Service Disconnect$2,128165 bids
- Electrical Ground$250149 bids
- Electrical Junction Box,Type 1$742148 bids
- Remove Electrical Services$730114 bids
- Electrical Service$975113 bids
372 observations
1 agency in 1 state · lettings Nov 8, 2022 – Feb 10, 2026
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|