Other698A000LS · lump sum
Construction Fuel (Maximum Bid Limited to $ 212,027.00)
LSPriced per contract — not a unit price
Median lump-sum amount
Moderate 5 winning bids≈$51,300per contractLow confidence
Treat this as a rough guide. Only 5 winning bids, and they are widely scattered.
- Winning bids
- 5
- Source documents
- 1
Winning bids only, as awarded. Nominal dollars. How we compute this
5Winning bids
1Agency
Jul 31, 2009Letting period
Where the number comes from
One of the 5 winning bids behind that median, with the agency’s own document one click away.
- Agency
- ALDOT · Alabama
- Letting
- Jul 31, 2009
- Quantity
- 1 LS
- Contractor
- Tomlin Construction, LLC
- Winning price
- $50,000 / LS
What’s behind $51,300
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 5 bids charted, so you can see clusters and outliers.
5 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Create free accountHave one? Sign in
Email only — no card. Search and medians stay open without an account.
Related items
Other other items priced per LS, ranked by how much evidence each has.
- Construction Engineering$15,0003,453 bids
- Roadway Construction Control$35,000794 bids
- Escrow of Bid Documents$1,00093 bids
- Partnering, DO Not Bid$6,00055 bids
- Plant Establishment Work (Minimum Bid)$150,00042 bids
- Monitoring of Construction-related Earthborne Vibrations$35,00039 bids
- Audio Visual Record of Construction Area$1,25034 bids
- Moving Item NO. 027$1,50032 bids
5 observations
1 agency in 1 state · lettings Jul 31, 2009
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|