Drainage998A000LS · lump sum
Construction Fuel (Maximum Bid Limited to $ 201,500.00) Trainee Hours at 80 Cents per Hour Contract Totals Alabama Department of Transportation Date: 01/29/01 Page: 008 -1 Vendor Ranking ERY Letting Date: 01/26/01 10:00 AM District: 06 Contract Description: Contract Time: 110 Working Days (Available Days) for Constructing the Interchange Modificationsr(Grade, Project(S): IM-85-1(143) Drain, Pave, Signing, Signals, and Lighting) at I-85 and S.R. #271 (Taylor Road) in Montgomery. Length - 0.529 Mi. Set-aside: Vendor Total % over Rank Number Name Bid Low Bid 1 18046 Reese & Howell, Inc. $ 1,408,330.79 100.0000% 2 04014 Dubose Construction, LLC $ 1,471,436.45 104.4809% 3 19095 Summit Development Company, L.L.C. $ 1,474,872.35 104.7249% 4 19047 Southeast Cherokee Construction, Inc. $ 1,484,399.46 105.4013% 5 14003 W. S. Newell, Inc. $ 1,557,802.89 110.6134% 6 16048 Walker Patton Company, Inc. $ 1,771,911.09 125.8164% Alabama Department of Transportation Date: 01/29/01 Page: 008 -2 Tabulation of Bids ERY Letting Date: 01/26/01 10:00 AM District: 06 Set-aside: Line NO / Item Code / ALT Item Description Quantity
LSPriced per contract — not a unit price
One winning bid
Single 1 winning bid$1,000per contract
One winning bid, one job. This is what one contractor bid on one contract, not a market rate. There is no range and no distribution to show. Read the document below before carrying it.
- Letting
- Jan 26, 2001
- Quantity
- 1 LS
- Agency
- ALDOT
Winning bids only, as awarded. Nominal dollars. How we compute this
What’s behind $1,000
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 1 bids charted, so you can see clusters and outliers.
1 observations
Agency, county, letting date, quantity and the price as printed.
1 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Create free accountHave one? Sign in
Email only — no card. Search and medians stay open without an account.
1Winning bid
1Agency
Jan 26, 2001Letting period
Where the number comes from
One of the 1 winning bids behind that median, with the agency’s own document one click away.
- Agency
- ALDOT · Alabama
- Letting
- Jan 26, 2001
- Quantity
- 1 LS
- Contractor
- Reese & Howell, Inc.
- Winning price
- $1,000 / LS
1 observation
1 agency in 1 state · lettings Jan 26, 2001
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
1 rows, each with its source document. Sign in to open them.Create free account