Bore/Jack __in Steel Casing Pipe-rock
Median winning unit price
Thin 4 winning bids≈$1,222/ LFLow confidence
- Winning bids
- 4
- Source documents
- 4
Winning bids only, as awarded. Nominal dollars. How we compute this
What’s behind $1,222
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 4 bids charted, so you can see clusters and outliers.
4 observations
Agency, county, letting date, quantity and the price as printed.
4 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Where the number comes from
One of the 4 winning bids behind that median, with the agency’s own document one click away.
- Agency
- TDOT · Davidson, Tennessee
- Letting
- May 13, 2022
- Quantity
- 254 LF
- Contractor
- Superior Construction Company Southeast, LLC
- Winning price
- $2,870 / LF
Median by quarter
EstimatorHow this item has priced over time, quarter by quarter, from the same rows as the headline figure.
See what Estimator adds4 observations
1 agency in 1 state · lettings Dec 2, 2016 – May 13, 2022
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|