Aggregate Surfacing (Aldot #410 or #467)
Median winning unit price
Deep 13 winning bids$15.00/ MTON
- Winning bids
- 13
- Source documents
- 7
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 13 winning bids behind that median, with the agency’s own document one click away.
- Agency
- ALDOT · Alabama
- Letting
- Jun 27, 2008
- Quantity
- 200 MTON
- Contractor
- Walker Patton Company, Inc.
- Winning price
- $21.00 / MTON
Median by quarter
EstimatorHow this item has priced over time, quarter by quarter, from the same rows as the headline figure.
See what Estimator addsWhat’s behind $15.00
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 13 bids charted, so you can see clusters and outliers.
13 observations
Agency, county, letting date, quantity and the price as printed.
7 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Related items
Other paving items priced per MTON, ranked by how much evidence each has.
- Aggregate Surfacing (Aldot #467, #410 Modified, or #57)$16.0011 bids
- Aggregate Surfacing (Aldot #410, #467, or #810)$20.5510 bids
- Aggregate Surfacing (Aldot #410 Modified or #467)$14.005 bids
- Aggregate Surfacing (Aldot #467 or #57)$27.5037 bids
- Aggregate Surfacing (Aldot #410 Modified)$19.2123 bids
- Aggregate Surfacing (Aldot #467)$16.657 bids
- Aggregate Surfacing (Aldot #467, #57 or #810)$44.804 bids
- Aggregate Surfacing (Aldot #57, #78, or #467)$23.004 bids
13 observations
1 agency in 1 state · lettings Jul 28, 2000 – Jun 27, 2008
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|
Something wrong with this price? Report it — the form arrives knowing which item you mean.