Other · awarded bid prices · Greenville County
24 inch white solid line (stop/diag line)-thermoplastic.-125 mil: cost per linear foot in Greenville County, SC
Listed by the agency as “24" White Solid Lines (Stop/Diag Lines)-THERMO.-125 MIL”.
The median awarded price is $9.43 per linear foot, from 18 winning bids on 18 public projects in Greenville County, SC (2023–2026). Half of the awarded prices fall between $8.56 and $13.88.
Cost by state › South Carolina › Greenville County › 24" White Solid Lines (Stop/Diag Lines)-THERMO.-125 MIL
Winning bids only, as printed in the agencies' bid tabulations (SCDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $7.50 in 2019 to $8.75 in 2025 (+17%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2019 | $7.50 | 5 |
| 2022 | $8.50 | 7 |
| 2023 | $10.18 | 6 |
| 2024 | $9.68 | 6 |
| 2025 | $8.75 | 9 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Apr 14, 2026 | SCDOT | 845 LF | $9.50 | Open bid tab, contract 2372300 ↗ |
| Nov 12, 2025 | SCDOT | 72 LF | $24.00 | Open bid tab, contract 2370000 ↗ |
| Nov 12, 2025 | SCDOT | 3140 LF | $8.75 | Open bid tab, contract 2373450 ↗ |
| Oct 14, 2025 | SCDOT | 11150 LF | $8.50 | Open bid tab, contract 2374680 ↗ |
| Sep 9, 2025 | SCDOT | 6670 LF | $9.50 | Open bid tab, contract 2372850 ↗ |
The same item across South Carolina: statewide figures. See every awarded price for this item on the 24" White Solid Lines (Stop/Diag Lines)-THERMO.-125 MIL item page.
Related items in Greenville County
- 4" Yellow Solid Lines(Pvt.Edge Lines) THERMO-90 Mil.: $0.825 per linear foot
- 4" White Solid Lines (Pvt. Edge Lines) Thermo.- 90 Mil.: $0.725 per linear foot
- 4" White Broken Lines(Gaps Excl.)Thermoplastic- 90 Mil.: $0.8 per linear foot
- 24" White Solid Lines (Stop/Diagonal Lines)-Fast Dry Paint: $1.02 per linear foot
- 4" White Solid Lines (Pvt. Edge Lines)-Fast Dry Paint: $0.15 per linear foot
- White Single Arrows (Lt, Strght, RT) THERMO.-125 Mil.: $100.00 per each
- Pedestrian Ramp Construction: $207.00 per square yard
- 8" White Solid Lines Thermoplastic - 125 Mil.: $2.75 per linear foot