Construction unit costs in Oregon

Median awarded unit prices for the 40 most-bid items on Oregon public projects, from winning bids in agency bid tabulations.

Cost by state › Oregon

ItemPerMedianMiddle halfWinning bids
Temporary Signssquare foot$26.00$17.75 – $32.62188
Temporary Barricades, Type IIIeach$190.00$150.00 – $223.00179
Temporary Plastic Drumseach$53.25$45.00 – $65.00176
Flaggershour$77.00$70.00 – $84.25172
Portable Changeable Message Signseach$6,000$3,000 – $10,000151
Aggregate Baseton$57.00$39.05 – $80.00125
Temporary Barricades, Type IIeach$70.00$60.00 – $91.50125
Sign Support Footingscubic yard$4,246$2,955 – $5,909121
Flagger Station Lightingeach$1,800$800.00 – $3,250117
Signs, Standard Sheeting, Sheet Aluminumsquare foot$34.00$28.25 – $44.00106
Sequential Arrow Signseach$2,000$1,000 – $4,000105
Inlet Protection, Type 3each$102.50$75.00 – $150.00104
Temporary Impact Attenuator, Truck Mountedeach$10,000$5,500 – $15,74998
Pavement Bar, Type B-hssquare foot$18.00$14.00 – $21.7597
Bridge Identification Markerseach$280.00$220.00 – $350.0094
Perforated Steel Square Tube Slip Base Sign Supportspound$9.02$6.67 – $12.1691
Pedestrian Channelizing Deviceslinear foot$27.00$18.00 – $35.0089
Contaminated Soil Disposalton$120.00$85.50 – $162.2586
Sediment Barrier, Type 3linear foot$6.90$5.00 – $10.0081
Perforated Steel Square Tube Anchor Sign Supportspound$8.27$6.19 – $12.7780
General Excavationcubic yard$50.00$29.98 – $80.0079
Concrete Walkssquare foot$11.50$10.00 – $16.6979
Traffic Control Supervisoreach$675.00$351.25 – $950.0078
Bar Removalsquare foot$8.96$6.06 – $16.5078
Permanent Seedingacre$10,500$5,250 – $24,00075
Temporary Stripinglinear foot$0.4$0.2 – $1.0073
Pavement Legend, Type B-hs: Arrowseach$425.00$380.00 – $512.5072
Subgrade Geotextilesquare yard$2.00$1.50 – $3.0369
Concrete Curbs, Curb and Gutterlinear foot$52.00$44.50 – $64.5067
Concrete Curbs, Standard Curblinear foot$45.00$36.75 – $61.5066
Mainline Video Inspectionlinear foot$15.00$10.00 – $28.0065
Extra for Asphalt Approacheseach$1,500$880.00 – $1,94464
Topsoilcubic yard$100.00$55.50 – $207.5058
Extra for New Curb Rampseach$1,263$850.00 – $2,53755
Truncated Domes on New Surfacessquare foot$45.00$38.00 – $50.0055
Asphalt Pavement Sawcuttinglinear foot$4.12$3.39 – $6.2552
Temporary Barrierlinear foot$32.00$22.25 – $50.0039
Structure Excavationcubic yard$89.17$63.05 – $289.2836
Removal of Guardraillinear foot$5.77$3.69 – $8.0126
Embankment in Placecubic yard$44.15$29.25 – $80.8216