Other · awarded bid prices
Temporary stripe: cost per linear foot in Oregon
Listed by the agency as “Temporary Striping”.
The median awarded price is $0.4 per linear foot, from 73 winning bids on 73 public projects in Oregon (2023–2026). Half of the awarded prices fall between $0.2 and $1.00.
Cost by state › Oregon › Temporary Striping
Winning bids only, as printed in the agencies' bid tabulations (ODOT). These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $0.2 in 2021 to $0.5 in 2026 (+150%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2021 | $0.2 | 33 |
| 2022 | $0.3 | 29 |
| 2023 | $0.4 | 22 |
| 2024 | $0.4 | 34 |
| 2025 | $0.475 | 18 |
| 2026 | $0.5 | 17 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 13, 2026 | ODOT | 3080 FOOT | $0.75 | 2026 bid data (zip) ↗ |
| Jul 23, 2026 | ODOT | 620 FOOT | $4.00 | 2026 bid data (zip) ↗ |
| Jul 23, 2026 | ODOT | 14138 FOOT | $0.4 | 2026 bid data (zip) ↗ |
| Jun 25, 2026 | ODOT | 200 FOOT | $2.50 | 2026 bid data (zip) ↗ |
| Jun 25, 2026 | ODOT | 3021 FOOT | $1.65 | 2026 bid data (zip) ↗ |
See every awarded price for this item, in all states, on the Temporary Striping item page.
Temporary Striping in other states
- Montana: median $0.25 (91 bids)
Related items in Oregon
- Temporary Plastic Drums: $53.25 per each
- Flaggers: $77.00 per hour
- Flagger Station Lighting: $1,800 per each
- Contaminated Soil Disposal: $120.00 per ton
- Bar Removal: $8.96 per square foot
- Mainline Video Inspection: $15.00 per linear foot
- Truncated Domes on New Surfaces: $45.00 per square foot
- Temporary Barrier: $32.00 per linear foot
Free account: new awarded prices for this item show on your watchlist.