Construction unit costs in Oklahoma

Median awarded unit prices for the 43 most-bid items on Oklahoma public projects, from winning bids in agency bid tabulations.

Cost by state › Oklahoma

ItemPerMedianMiddle halfWinning bids
Unclassified Excavationcubic yard$9.18$7.00 – $15.56310
Reinforcing Steelpound$1.58$1.30 – $2.20297
Class AA Concretecubic yard$713.50$570.00 – $947.86277
Temporary Silt Fencelinear foot$3.15$2.50 – $4.99247
Solid Slab Soddingsquare yard$3.48$2.70 – $5.61220
Traffic Bound Surface Course Type Eton$43.34$34.00 – $57.15217
Class C Concretecubic yard$430.56$356.88 – $716.38215
Sealer Crack Preparationlinear foot$4.30$3.52 – $5.00204
Temporary Silt Dikelinear foot$15.12$11.39 – $22.05188
Unclassified Borrowcubic yard$11.25$8.75 – $18.00187
Vegetative Mulchingacre$990.00$692.50 – $2,450178
Traffic Stripe(MULTI-POLY.)(6" Wide)linear foot$0.91$0.67 – $1.64176
Aggregate Base Type Acubic yard$75.00$60.00 – $83.00173
Cold Milling Pavementsquare yard$4.00$2.25 – $8.10172
Water Repellent (Visually Inspected)square yard$4.65$4.00 – $5.63168
Clsm Backfillcubic yard$215.00$180.00 – $288.56160
Class A Concretecubic yard$776.99$635.84 – $1,029158
Sheet Aluminum Signssquare foot$36.00$29.00 – $50.00154
Superpave, Type S4(PG 64-22 OK)ton$132.47$112.25 – $163.00153
Tack Coatgallon$3.77$3.02 – $5.00148
Superpave, Type S3(PG 64-22 OK)ton$113.36$98.81 – $137.62142
Pavement Mrkng.removal(traf.strp)linear foot$0.6$0.355 – $1.40142
Type I-A Plain Riprapton$62.00$50.00 – $63.52139
Substructure Excavation Commoncubic yard$20.00$12.00 – $30.00137
Removal of Asphalt Pavementsquare yard$7.50$5.25 – $10.82131
Traffic Stripe(MULTI-POLY.)(24" Wide)linear foot$11.75$6.02 – $20.00131
Epoxy Coated Reinforcing Steelpound$1.66$1.50 – $1.85122
6" Perforated Pipe Underdrain Roundlinear foot$30.00$26.00 – $40.80117
Saw-cut Groovingsquare yard$5.15$4.60 – $6.44116
Structural Steelpound$4.00$3.00 – $5.77113
6" Non-perf.Pipe Underdrain Rnd.linear foot$30.00$24.02 – $37.75112
Sawing Pavementlinear foot$4.00$3.00 – $6.70111
Deliver Portable Longitudinal Barrierlinear foot$25.00$18.31 – $33.50111
Sealed Expansion Jointslinear foot$362.62$325.00 – $490.00109
Traffic STRIPE(MULTI-POLY.)(4" Wide)linear foot$0.75$0.5 – $1.92108
Structural Excavation Unclassifiedcubic yard$33.17$25.00 – $43.60106
Beam Guardrail W-beam Singlelinear foot$32.04$28.50 – $37.10105
Elastomeric Coatingsquare foot$18.50$16.00 – $22.00105
Approach Slabsquare yard$284.40$250.00 – $315.00102
Removal of Guardraillinear foot$5.00$4.00 – $6.0490
Mowingacre$300.00$200.00 – $425.0089
Structural Concretecubic yard$1,100$570.73 – $1,68062
Removal of Fencelinear foot$2.50$1.88 – $5.7027