Paving · awarded bid prices · Greene County
Type 5 Aggregate for Base (6 in. Thick): cost per square yard in Greene County, MO
The median awarded price is $12.11 per square yard, from 22 winning bids on 15 public projects in Greene County, MO (2021–2026). Half of the awarded prices fall between $10.03 and $13.98.
Cost by state › Missouri › Greene County › Type 5 Aggregate for Base (6 in. Thick)
$12.11median per square yard
$10.03 – $13.98middle half (25th–75th percentile)
22winning bids, 15 source documents
2021–2026lettings covered (last 5 years)
Winning bids only, as printed in the agencies' bid tabulations (MoDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Mar 20, 2026 | MoDOT | 403 SQYD | $20.00 | Open the source page, contract 260320-G01 |
| Oct 17, 2025 | MoDOT | 14475 SQYD | $12.94 | Open the source page, contract 251017-G02 |
| Aug 15, 2025 | MoDOT | 672 SQYD | $20.00 | Open the source page, contract 250815-G02 |
| Mar 14, 2025 | MoDOT | 4729 SQYD | $13.70 | Open the source page, contract 250314-G03 |
| Dec 13, 2024 | MoDOT | 22043 SQYD | $11.50 | Open the source page, contract 241213-G02 |
See every awarded price for this item on the Type 5 Aggregate for Base (6 in. Thick) item page.
Related items in Greene County
- Tack Coat: $2.86 per gallon
- Type 5 Aggregate for Base (4 in. Thick): $16.00 per square yard
- Concrete Curb Ramp: $172.00 per square yard
- Pull Box, Concrete, Standard: $3,240 per each
- Concrete Sidewalk, 4 in.: $70.00 per square yard
- Type 1 Aggregate for Base (4 in. Thick): $14.55 per square yard