Tack Coat: cost per gallon in Greene County, MO
The median awarded price is $2.86 per gallon, from 29 winning bids on 15 public projects in Greene County, MO (2021–2026). Half of the awarded prices fall between $2.67 and $3.20.
Cost by state › Missouri › Greene County › Tack Coat
Winning bids only, as printed in the agencies' bid tabulations (MoDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $2.27 in 2019 to $3.40 in 2024 (+50%).
| Year | Median per gallon | Winning bids |
|---|---|---|
| 2019 | $2.27 | 7 |
| 2020 | $2.27 | 10 |
| 2023 | $2.86 | 14 |
| 2024 | $3.40 | 6 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Mar 20, 2026 | MoDOT | 113 GAL | $4.00 | Open the source page, contract 260320-G01 |
| Oct 17, 2025 | MoDOT | 22529 GAL | $2.70 | Open the source page, contract 251017-G05 |
| Mar 14, 2025 | MoDOT | 185 GAL | $2.50 | Open the source page, contract 250314-G03 |
| Dec 13, 2024 | MoDOT | 13844 GAL | $3.00 | Open the source page, contract 241213-G02 |
| Nov 15, 2024 | MoDOT | 235 GAL | $2.50 | Open the source page, contract 241115-G3A |
The same item across Missouri: statewide figures. See every awarded price for this item on the Tack Coat item page.
Related items in Greene County
- Type 5 Aggregate for Base (4 in. Thick): $16.00 per square yard
- Concrete Curb Ramp: $172.00 per square yard
- Type 5 Aggregate for Base (6 in. Thick): $12.11 per square yard
- Pull Box, Concrete, Standard: $3,240 per each
- Concrete Sidewalk, 4 in.: $70.00 per square yard
- Type 1 Aggregate for Base (4 in. Thick): $14.55 per square yard