Traffic · awarded bid prices · Greene County
Preformed Thermoplastic Pavement Marking, 30 in White Midblock: cost per each in Greene County, MO
The median awarded price is $180.00 per each, from 21 winning bids on 12 public projects in Greene County, MO (2021–2025). Half of the awarded prices fall between $175.00 and $204.10.
Cost by state › Missouri › Greene County › Preformed Thermoplastic Pavement Marking, 30 in White Midblock
Winning bids only, as printed in the agencies' bid tabulations (MoDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $180.00 in 2023 to $184.00 in 2024 (+2%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2023 | $180.00 | 11 |
| 2024 | $184.00 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| May 16, 2025 | MoDOT | 78 EA | $319.00 | Open the source page, contract 250516-G03 |
| Nov 15, 2024 | MoDOT | 63 EA | $180.00 | Open the source page, contract 241115-G3A |
| Apr 19, 2024 | MoDOT | 545 EA | $174.00 | Open the source page, contract 240419-G05 |
| Sep 15, 2023 | MoDOT | 26 EA | $225.00 | Open the source page, contract 230915-G05 |
| May 19, 2023 | MoDOT | 15 EA | $275.00 | Open the source page, contract 230519-G04 |
See every awarded price for this item on the Preformed Thermoplastic Pavement Marking, 30 in White Midblock item page.
Related items in Greene County
- Preformed Thermoplastic Pavement Marking, Left/Right Arrow: $265.75 per each
- 4 In. Yellow Standard Waterborne Pavement Marking Paint, Type P Beads: $0.4 per linear foot
- 4 In. White Standard Waterborne Pavement Marking Paint, Type P Beads: $0.425 per linear foot
- Construction Signs: $7.88 per square foot
- 6 In. Yellow High Build Waterborne Pavement Marking Paint, Type L Beads: $0.33 per linear foot
- Pavement Marking Removal (Symbols): $102.10 per each
- Preformed Thermoplastic Pavement Marking, 12 in White, Yield Line Triangles: $53.30 per each
- Directional Indicator Barricade: $77.88 per each