The median awarded price is $80.00 per ton, from 21 winning bids on 21 public projects in Will County, IL (2022–2026). Half of the awarded prices fall between $78.00 and $100.00.
Cost by state › Illinois › Will County › Hma Bc Il-19.0 N50
$80.00median per ton
$78.00 – $100.00middle half (25th–75th percentile)
21winning bids, 21 source documents
2022–2026lettings covered (last 5 years)
Winning bids only, as printed in the agencies' bid tabulations (IDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Feb 27, 2026 | IDOT | 18 TON | $200.00 | Open bid tab, 61M25 ↗ |
| Feb 27, 2026 | IDOT | 1360 TON | $82.00 | Open bid tab, 62R23 ↗ |
| Jan 16, 2026 | IDOT | 409 TON | $79.00 | Open bid tab, 62F94 ↗ |
| Sep 19, 2025 | IDOT | 804 TON | $77.00 | Open bid tab, 62R22 ↗ |
| Apr 25, 2025 | IDOT | 431 TON | $90.00 | Open bid tab, 61K44 ↗ |
See every awarded price for this item on the Hma Bc Il-19.0 N50 item page.
Related items in Will County
- Sidewalk Rem: $3.00 per square foot
- Long Joint Sealant: $3.70 per linear foot
- Pc Conc Sidewalk 5: $10.00 per square foot
- Pavement Rem: $15.00 per square yard
- Hma Sc Il-9.5 D N70: $90.00 per ton
- Agg Subgrade Impr 12: $20.00 per square yard
- Agg Subgrade Improve: $47.00 per cubic yard
- Comb Curb Gutter Rem: $10.00 per linear foot