Earthwork · awarded bid prices · Lake County

Trench Backfill: cost per cubic yard in Lake County, IL

The median awarded price is $52.50 per cubic yard, from 16 winning bids on 16 public projects in Lake County, IL (2024–2026). Half of the awarded prices fall between $40.00 and $76.70.

Cost by state › Illinois › Lake County › Trench Backfill

$52.50median per cubic yard
$40.00 – $76.70middle half (25th–75th percentile)
16winning bids, 16 source documents
2024–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (IDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $41.00 in 2020 to $47.00 in 2025 (+15%).

YearMedian per cubic yardWinning bids
2020$41.005
2021$42.0010
2022$38.005
2023$60.208
2024$55.007
2025$47.005

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Apr 24, 2026IDOT15 CU YD$200.00Open bid tab, 61M41 ↗
Feb 27, 2026IDOT50 CU YD$82.69Open bid tab, 62T82 ↗
Jan 16, 2026IDOT134 CU YD$45.00Open bid tab, 61L42 ↗
Jan 16, 2026IDOT1362 CU YD$70.00Open bid tab, 61M08 ↗
Sep 19, 2025IDOT8 CU YD$23.00Open bid tab, 61K52 ↗

The same item across Illinois: statewide figures. See every awarded price for this item on the Trench Backfill item page.