Perimeter erosion bar: cost per linear foot in Lake County, IL
Listed by the agency as “Perimeter Eros Bar”.
The median awarded price is $3.25 per linear foot, from 25 winning bids on 25 public projects in Lake County, IL (2023–2026). Half of the awarded prices fall between $2.75 and $3.95.
Cost by state › Illinois › Lake County › Perimeter Eros Bar
Winning bids only, as printed in the agencies' bid tabulations (IDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $2.25 in 2021 to $3.67 in 2026 (+63%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2021 | $2.25 | 10 |
| 2022 | $2.80 | 10 |
| 2023 | $2.49 | 11 |
| 2024 | $3.00 | 9 |
| 2025 | $2.80 | 7 |
| 2026 | $3.67 | 8 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jun 12, 2026 | IDOT | 1067 FOOT | $4.35 | Open bid tab, 80D46 ↗ |
| Apr 24, 2026 | IDOT | 2975 FOOT | $3.70 | Open bid tab, 61M41 ↗ |
| Feb 27, 2026 | IDOT | 2608 FOOT | $4.00 | Open bid tab, 62W78 ↗ |
| Feb 27, 2026 | IDOT | 661 FOOT | $3.95 | Open bid tab, 62T82 ↗ |
| Jan 16, 2026 | IDOT | 1610 FOOT | $3.65 | Open bid tab, 61L19 ↗ |
The same item across Illinois: statewide figures. See every awarded price for this item on the Perimeter Eros Bar item page.
Related items in Lake County
- Temp Info Signing: $18.00 per square foot
- Bit Matls Tack Ct: $0.01 per pound
- Thpl Pvt Mk Line 4: $1.10 per linear foot
- Non Spl Waste Disposl: $80.00 per cubic yard
- Soil Disposal Analy: $1,280 per each
- Thpl Pvt Mk Line 12: $3.32 per linear foot
- Thpl Pvt Mk Line 24: $6.05 per linear foot
- Thpl Pvt Mk Line 6: $1.65 per linear foot