Skip to content
Hubstake

Earthwork · awarded bid prices · Cook County

Trench Backfill: cost per cubic yard in Cook County, IL

The median awarded price is $58.50 per cubic yard, from 106 winning bids on 106 public projects in Cook County, IL (2023–2026). Half of the awarded prices fall between $35.75 and $84.00.

Cost by state › Illinois › Cook County › Trench Backfill

$58.50median per cubic yard
$35.75 – $84.00middle half (25th–75th percentile)
106winning bids, 106 source documents
2023–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (IDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $52.00 in 2021 to $62.00 in 2026 (+19%).

YearMedian per cubic yardWinning bids
2021$52.0027
2022$55.0023
2023$65.0029
2024$48.0031
2025$60.0033
2026$62.0038

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Sep 18, 2026IDOT36 CU YD$20.00Open bid tab, 62V90 ↗
Jul 31, 2026IDOT65 CU YD$23.00Open bid tab, 61K19 ↗
Jul 31, 2026IDOT92 CU YD$64.00Open bid tab, 61K85 ↗
Jul 31, 2026IDOT59 CU YD$118.00Open bid tab, 62J64 ↗
Jul 31, 2026IDOT37 CU YD$60.00Open bid tab, 62T84 ↗