Earthwork · awarded bid prices · Polk County
Embankment: cost per cubic yard in Polk County, FL
The median awarded price is $63.04 per cubic yard, from 15 winning bids on 15 public projects in Polk County, FL (2023–2026). Half of the awarded prices fall between $43.36 and $103.51.
Cost by state › Florida › Polk County › Embankment
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $29.00 in 2019 to $70.61 in 2025 (+143%).
| Year | Median per cubic yard | Winning bids |
|---|---|---|
| 2019 | $29.00 | 5 |
| 2023 | $116.10 | 5 |
| 2024 | $53.21 | 7 |
| 2025 | $70.61 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Mar 25, 2026 | FDOT | 114.6 CY | $106.82 | Open bid tab, T1928 ↗ |
| Aug 27, 2025 | FDOT | 66.8 CY | $70.96 | Open bid tab, T1918 ↗ |
| Jul 30, 2025 | FDOT | 164.8 CY | $100.21 | Open bid tab, T1921 ↗ |
| May 28, 2025 | FDOT | 106 CY | $50.00 | Open bid tab, T1911 ↗ |
| Feb 26, 2025 | FDOT | 1997.8 CY | $46.81 | Open bid tab, T1892 ↗ |
The same item across Florida: statewide figures. See every awarded price for this item on the Embankment item page.
Related items in Polk County
- Regular Excavation: $62.09 per cubic yard