Structures · awarded bid prices · Miami-dade County

Guardrail Transition Connection: cost per each in Miami-dade County, FL

The median awarded price is $3,177 per each, from 24 winning bids on 16 public projects in Miami-dade County, FL (2021–2026). Half of the awarded prices fall between $2,184 and $3,865.

Cost by state › Florida › Miami-dade County › Guardrail Transition Connection

$3,177median per each
$2,184 – $3,865middle half (25th–75th percentile)
24winning bids, 16 source documents
2021–2026lettings covered (last 5 years)

Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $3,300 in 2022 to $2,392 in 2023 (-28%).

YearMedian per eachWinning bids
2022$3,3007
2023$2,3927

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Sep 30, 2026FDOT3 EA$1,720Open bid tab, T6398 ↗
Jul 29, 2026FDOT2 EA$3,000Open bid tab, T6595 ↗
Mar 25, 2026FDOT1 EA$2,900Open bid tab, T6589 ↗
Mar 25, 2026FDOT2 EA$3,840Open bid tab, T6591 ↗
Dec 3, 2025FDOT2 EA$4,410Open bid tab, T6615 ↗

See every awarded price for this item on the Guardrail Transition Connection item page.