Street Lighting · awarded bid prices · Hillsborough County
Lighting Conductors, F&I: cost per linear foot in Hillsborough County, FL
The median awarded price is $2.90 per linear foot, from 18 winning bids on 13 public projects in Hillsborough County, FL (2024–2026). Half of the awarded prices fall between $2.58 and $4.00.
Cost by state › Florida › Hillsborough County › Lighting Conductors, F&I
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $2.10 in 2020 to $2.90 in 2025 (+38%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2020 | $2.10 | 5 |
| 2021 | $1.94 | 8 |
| 2024 | $2.75 | 11 |
| 2025 | $2.90 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| May 20, 2026 | FDOT | 690 LF | $3.40 | Open bid tab, T7595 ↗ |
| Mar 25, 2026 | FDOT | 1738 LF | $4.20 | Open bid tab, T7586 ↗ |
| Dec 3, 2025 | FDOT | 4868 LF | $2.90 | Open bid tab, T7559 ↗ |
| Jun 11, 2025 | FDOT | 1905 LF | $2.00 | Open bid tab, T7563 ↗ |
| Jun 11, 2025 | FDOT | 1914 LF | $3.18 | Open bid tab, T7564 ↗ |
See every awarded price for this item on the Lighting Conductors, F&I item page.
Related items in Hillsborough County
- Conduit, Furnish & Install: $43.50 per linear foot
- Conduit, Furnish & Install, Open: $28.00 per linear foot
- Pull & Splice Box, F&I, 13" x 24": $1,565 per each
- Prestressed Concrete Pole, F&I: $2,682 per each
- Electrical Service Wire, Furnish: $10.50 per linear foot
- Electrical Service Disconnect: $1,414 per each
- Aluminum Signals Pole, Pedestal: $2,797 per each