Paving · awarded bid prices · Rock County
Construction Staking Subgrade: cost per linear foot in Rock County, WI
The median awarded price is $0.01 per linear foot, from 17 winning bids on 17 public projects in Rock County, WI (2024–2026). Half of the awarded prices fall between $0.01 and $0.01.
Cost by state › Wisconsin › Rock County › Construction Staking Subgrade
Winning bids only, as printed in the agencies' bid tabulations (WisDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $0.105 in 2020 to $0.01 in 2026 (-90%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2020 | $0.105 | 6 |
| 2021 | $0.01 | 7 |
| 2024 | $0.01 | 7 |
| 2025 | $0.01 | 5 |
| 2026 | $0.01 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 11, 2026 | WisDOT | 2411 LF | $0.01 | Open bid tab, letting 20260811, call 003 |
| May 12, 2026 | WisDOT | 8706 LF | $0.01 | Open bid tab, letting 20260512, call 002 |
| May 12, 2026 | WisDOT | 237 LF | $0.01 | Open bid tab, letting 20260512, call 003 |
| May 12, 2026 | WisDOT | 100 LF | $0.01 | Open bid tab, letting 20260512, call 004 |
| Mar 10, 2026 | WisDOT | 6010 LF | $0.01 | Open bid tab, letting 20260310, call 010 |
The same item across Wisconsin: statewide figures. See every awarded price for this item on the Construction Staking Subgrade item page.
Related items in Rock County
- Sawing Asphalt: $1.49 per linear foot
- Tack Coat: $2.67 per gallon
- Base Aggregate Dense 1 1/4-Inch: $15.00 per ton
- Construction Staking Curb Gutter and Curb & Gutter: $2.00 per linear foot
- Removing Curb & Gutter: $7.03 per linear foot