Drainage · awarded bid prices · Outagamie County
Inlet 4-ft diameter: cost per each in Outagamie County, WI
Listed by the agency as “Inlets 4-FT Diameter”.
The median awarded price is $3,348 per each, from 18 winning bids on 18 public projects in Outagamie County, WI (2023–2026). Half of the awarded prices fall between $2,836 and $3,818.
Cost by state › Wisconsin › Outagamie County › Inlets 4-FT Diameter
Winning bids only, as printed in the agencies' bid tabulations (WisDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $3,275 in 2023 to $3,348 in 2025 (+2%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2023 | $3,275 | 7 |
| 2025 | $3,348 | 8 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jul 14, 2026 | WisDOT | 1 EACH | $3,687 | Open bid tab, letting 20260714, call 005 |
| Mar 10, 2026 | WisDOT | 5 EACH | $3,795 | Open bid tab, letting 20260310, call 023 |
| Mar 10, 2026 | WisDOT | 12 EACH | $3,825 | Open bid tab, letting 20260310, call 045 |
| Feb 10, 2026 | WisDOT | 67 EACH | $2,020 | Open bid tab, letting 20260210, call 022 |
| Dec 9, 2025 | WisDOT | 12 EACH | $2,945 | Open bid tab, letting 20251209, call 024 |
See every awarded price for this item on the Inlets 4-FT Diameter item page.
Related items in Outagamie County
- Culvert Pipe Checks: $15.00 per each
- Inlet Protection Type C: $70.00 per each
- Markers Culvert End: $72.50 per each
- Removing Small Pipe Culverts: $517.50 per each
- Removing Inlets: $384.00 per each
- Riprap Medium: $90.00 per cubic yard
- Inlet Covers Type H: $739.50 per each
- Inlets 2x3-FT: $2,674 per each