Traffic · awarded bid prices · Milwaukee County
Marking Curb Epoxy: cost per linear foot in Milwaukee County, WI
The median awarded price is $8.20 per linear foot, from 32 winning bids on 32 public projects in Milwaukee County, WI (2023–2026). Half of the awarded prices fall between $7.88 and $10.00.
Cost by state › Wisconsin › Milwaukee County › Marking Curb Epoxy
$8.20median per linear foot
$7.88 – $10.00middle half (25th–75th percentile)
32winning bids, 32 source documents
2023–2026lettings covered (last 3 years)
Winning bids only, as printed in the agencies' bid tabulations (WisDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $8.00 in 2021 to $7.87 in 2026 (-2%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2021 | $8.00 | 7 |
| 2022 | $8.25 | 7 |
| 2023 | $9.25 | 8 |
| 2024 | $8.23 | 10 |
| 2025 | $8.16 | 15 |
| 2026 | $7.87 | 6 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Sep 15, 2026 | WisDOT | 4664 LF | $6.47 | Open bid tab, letting 20260915, call 007 |
| Jul 14, 2026 | WisDOT | 2046 LF | $7.50 | Open bid tab, letting 20260714, call 004 |
| Mar 10, 2026 | WisDOT | 285 LF | $7.19 | Open bid tab, letting 20260310, call 016 |
| Feb 10, 2026 | WisDOT | 31 LF | $8.50 | Open bid tab, letting 20260210, call 009 |
| Feb 10, 2026 | WisDOT | 130 LF | $8.25 | Open bid tab, letting 20260210, call 014 |
See every awarded price for this item on the Marking Curb Epoxy item page.
Related items in Milwaukee County
- Traffic Control Barricades Type III: $0.53 per day
- Traffic Control Signs: $0.35 per day
- Traffic Control: $19,475 per each
- Traffic Control Warning Lights Type A: $0.1 per day
- Traffic Control Drums: $0.15 per day
- Traffic Control Signs Pcms: $35.00 per day
- Traffic Control Warning Lights Type C: $0.1 per day
- Marking Arrow Epoxy: $225.00 per each