Other · awarded bid prices · Marathon County
MGS Thrie Beam Transition: cost per linear foot in Marathon County, WI
The median awarded price is $91.00 per linear foot, from 22 winning bids on 22 public projects in Marathon County, WI (2023–2026). Half of the awarded prices fall between $86.47 and $96.00.
Cost by state › Wisconsin › Marathon County › MGS Thrie Beam Transition
Winning bids only, as printed in the agencies' bid tabulations (WisDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $97.44 in 2023 to $98.50 in 2026 (+1%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2023 | $97.44 | 6 |
| 2024 | $89.10 | 5 |
| 2025 | $94.50 | 11 |
| 2026 | $98.50 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 11, 2026 | WisDOT | 300 LF | $87.00 | Open bid tab, letting 20260811, call 017 |
| May 12, 2026 | WisDOT | 157.6 LF | $90.00 | Open bid tab, letting 20260512, call 014 |
| Mar 10, 2026 | WisDOT | 157.6 LF | $98.89 | Open bid tab, letting 20260310, call 032 |
| Mar 10, 2026 | WisDOT | 157.6 LF | $98.50 | Open bid tab, letting 20260310, call 033 |
| Jan 13, 2026 | WisDOT | 157.6 LF | $98.50 | Open bid tab, letting 20260113, call 029 |
See every awarded price for this item on the MGS Thrie Beam Transition item page.
Related items in Marathon County
- Geotextile Type HR: $5.55 per square yard
- Bar Steel Reinforcement HS Coated Structures: $1.37 per pound
- Drilled Tie Bars: $13.89 per each
- Temporary Ditch Checks: $9.00 per linear foot
- Pipe Underdrain Wrapped 6-Inch: $6.50 per linear foot
- Turbidity Barriers: $48.15 per square yard
- Geotextile Type DF Schedule a: $4.83 per square yard
- Bar Steel Reinforcement HS Structures: $1.26 per pound