Remove small road sign support&assembly: cost per each in Smith County, TX

Listed by the agency as “Remove SM RD SN Sup&Am”.

The median awarded price is $110.00 per each, from 27 winning bids on 27 public projects in Smith County, TX (2022–2026). Half of the awarded prices fall between $98.85 and $225.00.

Cost by state › Texas › Smith County › Remove SM RD SN Sup&Am

$110.00median per each
$98.85 – $225.00middle half (25th–75th percentile)
27winning bids, 27 source documents
2022–2026lettings covered (last 5 years)

Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $250.00 in 2022 to $99.50 in 2026 (-60%).

YearMedian per eachWinning bids
2022$250.005
2023$135.3812
2026$99.506

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Jul 2, 2026TxDOT109 EA$52.50line 195 ↗
Jul 1, 2026TxDOT123 EA$95.00line 190 ↗
Jun 2, 2026TxDOT32 EA$99.00line 52 ↗
Apr 8, 2026TxDOT2 EA$110.00line 53 ↗
Mar 5, 2026TxDOT9 EA$100.00line 27 ↗