Skip to content
Hubstake

Traffic · awarded bid prices · Hidalgo County

Wk zn pavement marking sht terminal (tab)type w: cost per each in Hidalgo County, TX

Listed by the agency as “WK ZN PAV MRK SHT Term (Tab)Ty W”.

The median awarded price is $1.22 per each, from 18 winning bids on 18 public projects in Hidalgo County, TX (2024–2026). Half of the awarded prices fall between $1.11 and $1.49.

Cost by state › Texas › Hidalgo County › WK ZN PAV MRK SHT Term (Tab)Ty W

$1.22median per each
$1.11 – $1.49middle half (25th–75th percentile)
18winning bids, 18 source documents
2024–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $1.00 in 2023 to $1.25 in 2026 (+25%).

YearMedian per eachWinning bids
2023$1.008
2025$1.267
2026$1.257

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Nov 3, 2026TxDOT7628 EA$1.13line 18 ↗
Oct 7, 2026TxDOT415 EA$5.00line 54 ↗
Aug 5, 2026TxDOT2400 EA$1.50line 89 ↗
Jun 3, 2026TxDOT6395 EA$1.00line 18 ↗
Jun 2, 2026TxDOT30 EA$1.25line 104 ↗

The same item across Texas: statewide figures. See every awarded price for this item on the WK ZN PAV MRK SHT Term (Tab)Ty W item page.