Structures · awarded bid prices · Hidalgo County
Downstream Anchor Terminal Section: cost per each in Hidalgo County, TX
The median awarded price is $1,515 per each, from 15 winning bids on 14 public projects in Hidalgo County, TX (2024–2026). Half of the awarded prices fall between $1,400 and $1,975.
Cost by state › Texas › Hidalgo County › Downstream Anchor Terminal Section
Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $1,800 in 2024 to $1,483 in 2025 (-18%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2024 | $1,800 | 5 |
| 2025 | $1,483 | 7 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| May 7, 2026 | TxDOT | 6 EA | $1,480 | line 109 ↗ |
| May 7, 2026 | TxDOT | 1 EA | $1,510 | line 115 ↗ |
| Apr 7, 2026 | TxDOT | 1 EA | $1,665 | line 16 ↗ |
| Dec 2, 2025 | TxDOT | 10 EA | $1,515 | line 18 ↗ |
| Sep 5, 2025 | TxDOT | 6 EA | $1,483 | line 16 ↗ |
The same item across Texas: statewide figures. See every awarded price for this item on the Downstream Anchor Terminal Section item page.
Related items in Hidalgo County
- Temp Sedmt Cont Fence (Install): $4.75 per linear foot
- Temp Sedmt Cont Fence (Remove): $1.60 per linear foot
- Remov Str (Pipe): $10.00 per linear foot
- MTL W-beam GD Fen (Tim Post): $29.49 per linear foot
- Remov Str (Set): $300.00 per each
- Remove Metal Beam Guard Fence: $4.00 per linear foot
- Guardrail End Treatment (Install): $3,480 per each