Remove str (inlet): cost per each in Collin County, TX

Listed by the agency as “Remov Str (Inlet)”.

The median awarded price is $1,000 per each, from 20 winning bids on 20 public projects in Collin County, TX (2022–2026). Half of the awarded prices fall between $665.00 and $1,049.

Cost by state › Texas › Collin County › Remov Str (Inlet)

$1,000median per each
$665.00 – $1,049middle half (25th–75th percentile)
20winning bids, 20 source documents
2022–2026lettings covered (last 5 years)

Winning bids only, as printed in the agencies' bid tabulations (TxDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $1,000 in 2022 to $1,000 in 2023 (+0%).

YearMedian per eachWinning bids
2022$1,0008
2023$1,0005

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Oct 6, 2026TxDOT3 EA$500.00line 49 ↗
Aug 6, 2026TxDOT4 EA$500.00line 72 ↗
Jul 2, 2026TxDOT3 EA$500.00line 65 ↗
Jun 10, 2026TxDOT2 EA$1,000line 8 ↗
Nov 6, 2025TxDOT4 EA$800.00line 59 ↗

See every awarded price for this item on the Remov Str (Inlet) item page.