Construction unit costs in Shelby County, TN

Median awarded unit prices for 21 items on public projects in Shelby County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Tennessee › Shelby County

ItemPerMedianMiddle halfWinning bidsLatest source document
Sign (construction)square foot$8.17$7.04 – $9.4330Oct 2, 2026, contract CN264060 ↗
Flexible Drums (Channelizing)each$42.75$35.00 – $49.5628Oct 2, 2026, contract CN264060 ↗
Arrow Board (Type C)each$1,588$1,126 – $1,90027May 8, 2026, contract CN264038 ↗
Mineral Aggregate, Type B Base, Grading (C or D)ton$57.86$49.44 – $79.4020Oct 3, 2025, contract CNZ265 ↗
Concrete Sidewalk 4-Inchsquare foot$17.10$9.64 – $19.1220Mar 20, 2026, contract CN264027 ↗
Interconnected Portable Barrier Raillinear foot$47.50$32.67 – $60.0020Mar 20, 2026, contract CN264031 ↗
Changeable Message Sign Uniteach$5,594$5,052 – $9,62520May 8, 2026, contract CN264038 ↗
Plastic Pavement Marking (Turn Lane Arrow)each$300.00$250.00 – $317.5517May 8, 2026, contract CN264038 ↗
Plastic Word Pavement Marking (Only)each$312.50$286.80 – $325.2016May 8, 2026, contract CN264038 ↗
Plastic Pavement Marking (Stop Line)linear foot$30.62$29.88 – $32.5716May 8, 2026, contract CN264038 ↗
Cold milling asphalt pavementton$26.00$22.50 – $45.9715May 8, 2026, contract CN264038 ↗
Snowplowable Raised Pavment Markers (MONO-DIR)(1 Color)each$50.50$50.25 – $52.9215May 8, 2026, contract CN264038 ↗
Plastic Pavement Marking (Longitudinal Cross-walk)linear foot$52.00$51.50 – $54.4915May 8, 2026, contract CN264038 ↗
Remove of asphalt pavementsquare yard$33.86$15.44 – $50.0014May 8, 2026, contract CN264038 ↗
Plastic pavement marking(channelization stripe)square yard$45.18$41.85 – $52.0914May 8, 2026, contract CN264038 ↗
Trackless Tack Coatton$1,000$840.00 – $1,21013May 8, 2026, contract CN264038 ↗
Warning Lights (type A)each$18.00$16.24 – $25.0013Aug 14, 2026, contract CN264054 ↗
Temporary Work Zone Crash Cushion (Mash TL-3)each$10,100$8,250 – $11,98812Oct 2, 2026, contract CN264060 ↗
Loop Wirelinear foot$2.04$2.00 – $2.0612Mar 20, 2026, contract CN264027 ↗
Temporary barricade (type iii)linear foot$18.62$14.62 – $20.5012Aug 14, 2026, contract CN264054 ↗
Saw Slotlinear foot$8.16$7.00 – $9.5512Mar 20, 2026, contract CN264027 ↗