Traffic · awarded bid prices · Rutherford County
Changeable Message Sign Unit: cost per each in Rutherford County, TN
The median awarded price is $5,652 per each, from 12 winning bids on 12 public projects in Rutherford County, TN (2024–2026). Half of the awarded prices fall between $4,655 and $5,916.
Cost by state › Tennessee › Rutherford County › Changeable Message Sign Unit
Winning bids only, as printed in the agencies' bid tabulations (TDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $5,025 in 2019 to $5,750 in 2025 (+14%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2019 | $5,025 | 6 |
| 2024 | $5,555 | 5 |
| 2025 | $5,750 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jun 26, 2026 | TDOT | 10 EACH | $11,690 | contract CN263057 ↗ |
| Feb 6, 2026 | TDOT | 2 EACH | $4,200 | contract CN263019 ↗ |
| Dec 5, 2025 | TDOT | 2 EACH | $5,307 | contract CNZ304 ↗ |
| Jun 27, 2025 | TDOT | 2 EACH | $5,750 | contract CNZ193 ↗ |
| Jun 27, 2025 | TDOT | 3 EACH | $5,800 | contract CNZ204 ↗ |
The same item across Tennessee: statewide figures. See every awarded price for this item on the Changeable Message Sign Unit item page.
Related items in Rutherford County
- Signs (Construction): $7.55 per square foot
- Plastic Pavement Marking (Stop Line): $20.02 per linear foot
- Plastic Pavement Marking (Turn Lane Arrow): $200.00 per each
- Plastic Pavement Marking(Channelization Striping): $35.00 per square yard