4 inch yellow solid line(pvt.edge line) thermoplastic-90 mil.: cost per linear foot in Lexington County, SC

Listed by the agency as “4" Yellow Solid Lines(Pvt.Edge Lines) THERMO-90 Mil.”.

The median awarded price is $0.5 per linear foot, from 16 winning bids on 16 public projects in Lexington County, SC (2023–2026). Half of the awarded prices fall between $0.458 and $0.962.

Cost by state › South Carolina › Lexington County › 4" Yellow Solid Lines(Pvt.Edge Lines) THERMO-90 Mil.

$0.5median per linear foot
$0.458 – $0.962middle half (25th–75th percentile)
16winning bids, 16 source documents
2023–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (SCDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $0.47 in 2022 to $0.85 in 2025 (+81%).

YearMedian per linear footWinning bids
2022$0.475
2024$0.57
2025$0.855

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Apr 14, 2026SCDOT31475 LF$0.5Open bid tab, contract 3270840 ↗
Jan 13, 2026SCDOT124805 LF$0.44Open bid tab, contract 3275880 ↗
Dec 9, 2025SCDOT3700 LF$0.85Open bid tab, contract 3265530 ↗
Sep 9, 2025SCDOT3900 LF$0.95Open bid tab, contract 3265540 ↗
Sep 9, 2025SCDOT172320 LF$0.48Open bid tab, contract 3273620 ↗