Cost by state
Construction unit costs in New Jersey
Median awarded unit prices for the 21 most-bid items on New Jersey public projects, from winning bids in agency bid tabulations.
| Item | Per | Median | Middle half | Winning bids |
|---|---|---|---|---|
| Traffic Marking Lines, 24" | linear foot | $5.29 | $4.80 – $7.19 | 130 |
| Traffic Stripes, 4" | linear foot | $0.6 | $0.47 – $1.00 | 124 |
| Removal Of Traffic Stripes | linear foot | $0.8 | $0.4 – $1.00 | 113 |
| Traffic Marking Lines, 8" | linear foot | $1.69 | $1.50 – $2.00 | 111 |
| Traffic Markings Symbols | square foot | $9.25 | $8.00 – $10.50 | 108 |
| 9" X 16" Concrete Vertical Curb | linear foot | $61.75 | $40.00 – $86.94 | 107 |
| Traffic Stripes, Latex, 4" | linear foot | $0.25 | $0.22 – $0.495 | 95 |
| Removal Of Traffic Markings | square foot | $3.15 | $1.50 – $4.62 | 95 |
| Rumble Strip | linear foot | $1.00 | $0.57 – $2.50 | 95 |
| Traffic Stripes, 8" | linear foot | $0.95 | $0.84 – $1.40 | 93 |
| Hma Milling, 3" Or Less | square yard | $5.05 | $2.62 – $8.12 | 92 |
| Detectable Warning Surface | square yard | $273.50 | $132.50 – $385.00 | 78 |
| Concrete Sidewalk, 4" Thick | square yard | $136.50 | $86.00 – $185.00 | 74 |
| Beam Guide Rail | linear foot | $40.00 | $33.25 – $50.00 | 70 |
| Hot Mix Asphalt 25 M 64 Base Course | ton | $125.00 | $90.00 – $210.00 | 65 |
| Removal Of Beam Guide Rail | linear foot | $1.11 | $1.00 – $4.00 | 62 |
| 3" Rigid Metallic Conduit | linear foot | $86.40 | $75.00 – $106.00 | 61 |
| Fertilizing And Seeding, Type A-3 | square yard | $1.75 | $0.75 – $2.30 | 59 |
| Reinforcement, Steel, Epoxy Coated | pound | $2.50 | $2.00 – $4.90 | 54 |
| Micro-Milling | square yard | $3.50 | $2.45 – $5.25 | 43 |
| Topsoil | square yard | $15.00 | $7.00 – $17.00 | 21 |
Agencies in New Jersey
- New Jersey Department of Transportation: 194,978 winning prices
- New Jersey Turnpike Authority: 7,456 winning prices