| Mobilization | ls | 89 | $615,000 | $972,000 | $5,000 – $4,500,000 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Furnishing Traffic Control Devices | ls | 75 | — | $230,000 | $10,000 – $7,004,605 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Construction Layout | ls | 65 | — | $7,500 | $0.01 – $1,500,000 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Progress Schedule | ls | 62 | $12,750 | $25,000 | $0.01 – $100,000 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Traffic Stripes, Long-Life, Thermoplastic | linear foot | 54 | $1.27 | $1.50 | $0.01 – $5.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Polymerized Joint Adhesive | linear foot | 54 | — | $1.05 | $0.01 – $21.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Furnishing Portable Variable Message Sign | each | 51 | — | $7,500 | $0.01 – $100,000 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Milled Rumble Strip | linear foot | 51 | — | $1.80 | $0.2 – $40.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Furnishing Truck with Mounted Attenuator | each | 48 | — | $25,000 | $0.01 – $75,000 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Traffic Protection Patrol, Part-Time | m.h. | 48 | — | $200.00 | $0.01 – $200.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Asphalt Concrete Lip Curb | linear foot | 46 | — | $35.00 | $0.01 – $400.00 | Mar 18, 2026, Open bid tab, contract T200.736 ↗ |
| Repair Truck Mounted Impact Attenuators | each | 45 | — | $5,500 | $0.01 – $30,000 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Berm Surfacing, 3 Inches Thick | square yard | 45 | $58.00 | $25.00 | $15.00 – $500.00 | May 15, 2026, Open bid tab, contract T200.904 ↗ |
| Beam Guide Rail | linear foot | 45 | $40.00 | $44.00 | $23.54 – $150.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Roadway Excavation, Earth | cubic yard | 43 | $85.00 | $60.00 | $0.01 – $500.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Traffic marking, line, long life, thermoplastic | linear foot | 43 | $1.25 | $1.50 | $0.01 – $430.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Maintain Field Office, Type B | mnth | 42 | $2,322 | $3,000 | $1.00 – $4,500 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Furnishing Truck with Mounted Attenuator for Engineer's Use | m.h. | 41 | — | $200.00 | $0.01 – $275.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Inlet Filter, Type 2 | each | 40 | $230.00 | $150.00 | $1.00 – $1,200 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Hot Mix Asphalt 12.5M76 Surface Course | ton | 40 | $256.50 | $117.00 | $74.10 – $1,275 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Placing and remove precast concrete construction barrier | linear foot | 39 | $35.00 | $35.00 | $5.00 – $80.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Furnishing Precast Concrete Construction Barrier | linear foot | 39 | — | $60.00 | $1.00 – $250.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Topsoil | square yard | 39 | $10.00 | $15.00 | $1.00 – $100.00 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Trackless Tack Coat | gallon | 38 | $6.00 | $5.25 | $0.01 – $60.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Disposal Of Regulated Material | ton | 38 | $50.00 | $25.00 | $0.01 – $200.00 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Remove of beam guide rail | linear foot | 38 | $4.00 | $1.00 | $1.00 – $30.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Traffic Stripes, Long Life, Epoxy Resin | linear foot | 38 | $1.50 | $1.50 | $0.6 – $50.00 | Mar 18, 2026, Open bid tab, contract T200.736 ↗ |
| Furnish Field Office, Type B | ls | 37 | $19,500 | $35,700 | $1.00 – $50,000 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Install, maintenance, and remove of lane closing | each | 37 | — | $8,000 | $0.01 – $11,000 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Clearing and Grubbing | ls | 37 | — | $320,000 | $0.01 – $1,350,000 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Test Pits | each | 36 | $600.00 | $500.00 | $0.01 – $4,325 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Flaggers | m.h. | 34 | — | $150.00 | $0.01 – $270.00 | Feb 25, 2026, Open bid tab, contract T100.723 ↗ |
| Stripe and marking remove, hydromilling | linear foot | 34 | $1.00 | $2.25 | $0.65 – $22.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Reset Frames | each | 33 | $640.00 | $2,400 | $250.00 – $5,000 | Feb 25, 2026, Open bid tab, contract T100.723 ↗ |
| Maintenance and Protection of Traffic on State, County, and Local Roadways | ls | 32 | $36,500 | $21,000 | $1.00 – $800,000 | Dec 16, 2025, Open bid tab, contract T100.744 ↗ |
| Heavy Duty Silt Fence | linear foot | 32 | $9.50 | $4.00 | $4.00 – $38.00 | Apr 10, 2026, Open bid tab, contract T200.618 ↗ |
| Temporary pavement stripe | linear foot | 31 | $1.00 | $1.15 | $0.3 – $4.00 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Raised Pavement Markers | each | 31 | $33.35 | $100.00 | $23.00 – $1,100 | Dec 16, 2025, Open bid tab, contract T100.744 ↗ |
| Hot Mix Asphalt 25 M 64 Base Course | ton | 30 | $187.50 | $300.00 | $100.00 – $1,000 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |
| Embankment, Common | cubic yard | 28 | $90.50 | $47.30 | $0.01 – $2,500 | Mar 26, 2026, Open bid tab, contract T200.901 ↗ |