Drainage · awarded bid prices · St. Charles County
Channelizer (Trim Line): cost per each in St. Charles County, MO
The median awarded price is $21.00 per each, from 12 winning bids on 11 public projects in St. Charles County, MO (2024–2025). Half of the awarded prices fall between $17.25 and $25.88.
Cost by state › Missouri › St. Charles County › Channelizer (Trim Line)
Winning bids only, as printed in the agencies' bid tabulations (MoDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $20.00 in 2019 to $18.00 in 2025 (-10%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2019 | $20.00 | 7 |
| 2021 | $20.00 | 6 |
| 2022 | $11.00 | 8 |
| 2023 | $21.00 | 8 |
| 2024 | $22.00 | 7 |
| 2025 | $18.00 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Sep 19, 2025 | MoDOT | 126 EA | $18.00 | Open the source page, contract 250919-F02 |
| Sep 19, 2025 | MoDOT | 80 EA | $7.00 | Open the source page, contract 250919-F03 |
| Jun 20, 2025 | MoDOT | 50 EA | $34.00 | Open the source page, contract 250620-F02 |
| May 16, 2025 | MoDOT | 261 EA | $20.00 | Open the source page, contract 250516-F06 |
| Jan 17, 2025 | MoDOT | 100 EA | $15.00 | Open the source page, contract 250117-F02 |