Advanced Warning Rail System: cost per each in St. Charles County, MO

The median awarded price is $46.15 per each, from 28 winning bids on 20 public projects in St. Charles County, MO (2022–2025). Half of the awarded prices fall between $25.00 and $50.44.

Cost by state › Missouri › St. Charles County › Advanced Warning Rail System

$46.15median per each
$25.00 – $50.44middle half (25th–75th percentile)
28winning bids, 20 source documents
2022–2025lettings covered (last 5 years)

Winning bids only, as printed in the agencies' bid tabulations (MoDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $45.00 in 2019 to $50.00 in 2024 (+11%).

YearMedian per eachWinning bids
2019$45.007
2021$7.626
2022$50.009
2023$25.0010
2024$50.007

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
May 16, 2025MoDOT8 EA$45.00Open the source page, contract 250516-F06
Jan 17, 2025MoDOT4 EA$45.00Open the source page, contract 250117-F02
Oct 18, 2024MoDOT2 EA$25.00Open the source page, contract 241018-F07
Apr 19, 2024MoDOT2 EA$35.00Open the source page, contract 240419-F03
Apr 19, 2024MoDOT2 EA$50.00Open the source page, contract 240419-F4A

The same item across Missouri: statewide figures. See every awarded price for this item on the Advanced Warning Rail System item page.