Other · awarded bid prices · St. Louis County
4 inch double solid line multi-component: cost per linear foot in St. Louis County, MN
Listed by the agency as “4" Double Solid Line Multi-Component”.
The median awarded price is $0.78 per linear foot, from 101 winning bids on 27 public projects in St. Louis County, MN (2023–2026). Half of the awarded prices fall between $0.76 and $0.86.
Cost by state › Minnesota › St. Louis County › 4" Double Solid Line Multi-Component
Winning bids only, as printed in the agencies' bid tabulations (St. Louis County). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $0.66 in 2022 to $0.74 in 2026 (+12%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2022 | $0.66 | 46 |
| 2023 | $0.9 | 8 |
| 2024 | $0.815 | 30 |
| 2025 | $0.78 | 46 |
| 2026 | $0.74 | 19 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jun 18, 2026 | St. Louis County | 236 LIN FT | $1.60 | Open bid tab, CP 0305-556182 ↗ |
| Jun 11, 2026 | St. Louis County | 11099 LIN FT | $0.85 | Open bid tab, CP 0021-439116; SP 0 ↗ |
| Jun 11, 2026 | St. Louis County | 135 LIN FT | $10.00 | Open bid tab, CP 0088-885444 ↗ |
| Apr 2, 2026 | St. Louis County | 19020 LIN FT | $0.74 | Open bid tab, CP 0000-953552 ↗ |
| Jan 15, 2026 | St. Louis County | 4612 LIN FT | $0.73 | Open bid tab, CP 0000-727547 ↗ |
See every awarded price for this item on the 4" Double Solid Line Multi-Component item page.
Related items in St. Louis County
- 6" Solid Line Multi-Component: $0.53 per linear foot
- 4" Solid Line Multi-Component: $0.4 per linear foot
- 4" Broken Line Multi-Component: $0.395 per linear foot
- Mail Box Support: $200.00 per each
- Calcium Chloride Solution: $1.70 per gallon
- Granular Bedding (Cv) (P): $49.00 per cubic yard
- 0.5 Cu Yd Shovel: $200.00 per hour
- Soil Bed Preparation: $630.00 per acre