| Reflectorized Raised Pavement Markers | each | $7.00 | $5.00 – $10.00 | 593 |
| Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | mile | $5,600 | $4,620 – $7,150 | 521 |
| Asphalt Concrete | ton | $154.00 | $129.25 – $215.00 | 477 |
| Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | mile | $2,000 | $1,320 – $3,100 | 427 |
| Asphalt Concrete, Drives, Turnouts and Miscellaneous | ton | $230.00 | $170.00 – $300.00 | 414 |
| Temporary Pavement Markings (Solid Line)(4" Width) | mile | $1,000 | $800.00 – $1,250 | 412 |
| Milling Asphalt Pavement | square yard | $4.10 | $2.97 – $9.00 | 397 |
| Temporary Silt Fencing | linear foot | $3.00 | $2.25 – $5.00 | 385 |
| Temporary Pavement Markings (Broken Line)(4" Width) (10' Length) | mile | $650.00 | $500.00 – $800.00 | 377 |
| Temporary Pavement Markings (Broken Line)(4" Width)(4' Length) | mile | $350.00 | $220.00 – $765.00 | 359 |
| Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | linear foot | $16.50 | $13.44 – $22.06 | 336 |
| Object Marker Assembly (Type 3) | each | $125.00 | $100.00 – $144.19 | 326 |
| Bedding Material | cubic yard | $158.00 | $125.00 – $200.00 | 313 |
| Removal of Existing Markings | mile | $8,500 | $4,983 – $13,625 | 288 |
| Mailboxes | each | $25.00 | $10.00 – $35.00 | 283 |
| Mailbox Supports (Single) | each | $275.00 | $230.00 – $325.00 | 280 |
| Borrow (Vehicular Measurement) | cubic yard | $55.00 | $30.00 – $95.53 | 273 |
| Hydro-seeding | acre | $3,795 | $3,000 – $6,500 | 269 |
| Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | linear foot | $35.00 | $32.00 – $39.87 | 266 |
| Aggregate Surface Course (Adjusted Vehicular Measurement) | cubic yard | $102.50 | $62.00 – $185.00 | 250 |
| Removal of Guardrail | linear foot | $13.00 | $9.00 – $16.00 | 245 |
| Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | cubic yard | $100.50 | $60.00 – $151.47 | 236 |
| Guard Rail Transitions (Double Thrie Beam) | linear foot | $132.00 | $118.00 – $140.00 | 227 |
| Rumble Strips (Shoulder/Edge) | mile | $1,000 | $498.88 – $1,200 | 224 |
| Removal of Concrete Walks and Drives | square yard | $26.00 | $20.00 – $41.62 | 222 |
| Plastic Pavement Legends and Symbols (Arrow - Left Turn) | each | $350.00 | $300.00 – $440.00 | 211 |
| Fertilizer | pound | $1.00 | $0.95 – $2.25 | 203 |
| Temporary Sediment Check Dams (Hay) | each | $175.00 | $153.50 – $226.50 | 203 |
| Temporary Pavement Markings (24" Width) | linear foot | $0.6 | $0.453 – $1.08 | 202 |
| Geotextile Fabric | square yard | $4.00 | $3.00 – $6.00 | 201 |
| Seeding | pound | $25.00 | $15.00 – $43.00 | 198 |
| Object Marker Assembly (Type 2) | each | $92.92 | $80.00 – $120.00 | 187 |
| Mulch (Vegetative) | ton | $1,500 | $900.00 – $3,896 | 184 |
| Guard Rail End Treatment, MASH, (TL-3 Tangent) | each | $4,000 | $3,650 – $4,250 | 179 |
| Plastic Pavement Legends and Symbols (Arrow - Right Turn) | each | $350.00 | $300.00 – $425.00 | 173 |
| Concrete Curb | linear foot | $40.00 | $22.56 – $60.00 | 164 |
| Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | linear foot | $4.00 | $3.00 – $4.50 | 161 |
| Concrete Collar | each | $2,200 | $1,500 – $2,800 | 149 |
| General Excavation | cubic yard | $35.00 | $21.50 – $70.00 | 139 |
| Portable Changeable Message Signs | each | $6,000 | $3,000 – $10,500 | 129 |
| Removal of Asphalt Pavement | square yard | $19.00 | $10.00 – $35.00 | 115 |
| Lime | ton | $384.00 | $315.00 – $450.00 | 111 |
| Embankment | cubic yard | $43.83 | $27.88 – $78.65 | 110 |
| Trenching and Backfilling | linear foot | $13.00 | $10.00 – $16.00 | 101 |
| Removal of Fence | linear foot | $5.00 | $3.00 – $8.00 | 53 |