Other · awarded bid prices · Various County
Arrow Panel: cost per each in Various County, KY
The median awarded price is $1,000 per each, from 41 winning bids on 35 public projects in Various County, KY (2022–2025). Half of the awarded prices fall between $500.00 and $1,250.
Cost by state › Kentucky › Various County › Arrow Panel
Winning bids only, as printed in the agencies' bid tabulations (KYTC). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $515.00 in 2019 to $1,000 in 2023 (+94%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2019 | $515.00 | 5 |
| 2021 | $1,500 | 6 |
| 2022 | $500.00 | 14 |
| 2023 | $1,000 | 26 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Oct 23, 2025 | KYTC | 2 EACH | $1.00 | Open bid tab, contract 25-4507 |
| Dec 14, 2023 | KYTC | 4 EACH | $500.00 | Open bid tab, contract 23-4009 |
| Dec 14, 2023 | KYTC | 4 EACH | $1,500 | Open bid tab, contract 23-4012 |
| Nov 16, 2023 | KYTC | 4 EACH | $1,000 | Open bid tab, contract 23-4017 |
| Nov 16, 2023 | KYTC | 4 EACH | $1,000 | Open bid tab, contract 23-4018 |
The same item across Kentucky: statewide figures. See every awarded price for this item on the Arrow Panel item page.
Related items in Various County
- Pave Striping-wb PAINT-4 in Y: $557.50 per mile
- Pave Striping-wb PAINT-4 in W: $515.00 per mile
- Steel Reinforcement-epoxy Coated: $2.11 per pound
- Steel Reinforcement: $2.00 per pound
- DGA Base: $53.50 per ton
- Law Enforcement Officer: $107.50 per hour
- Pave Striping-wb PAINT-6 IN Y: $790.00 per mile
- Pave Striping-temp REM Tape-w: $1.00 per linear foot