| Excavation, Class 20 | cubic yard | $24.00 | $14.00 – $41.25 | 52 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Portable Dynamic Message Sign (Pdms) | day | $125.00 | $75.00 – $175.00 | 52 | Sep 15, 2026, contract 77-0654-184 ↗ |
| Safety Closure | each | $200.00 | $105.75 – $250.00 | 51 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Reinforced steel | pound | $2.33 | $1.71 – $2.50 | 48 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Remove of pavement | square yard | $15.68 | $11.33 – $22.75 | 46 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Reinforced steel (epoxy coated) | pound | $1.75 | $1.45 – $3.00 | 45 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Remove of perimeter and slope or ditch check sediment control device | linear foot | $0.25 | $0.2 – $0.5 | 42 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Paint pavement marking, waterborne or solvent-based | station | $56.00 | $28.12 – $125.00 | 38 | Sep 15, 2026, contract 77-0654-184 ↗ |
| Grooves cut for pavement marking | station | $65.00 | $33.50 – $115.00 | 35 | Sep 15, 2026, contract 77-0654-184 ↗ |
| Excavation, Class 10, Roadway and Borrow | cubic yard | $8.45 | $5.00 – $14.75 | 34 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Topsoil, Strip, Salvage and Spread | cubic yard | $8.00 | $6.65 – $14.79 | 34 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Revetment, Class E | ton | $75.00 | $64.92 – $81.00 | 31 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Flaggers | each | $575.00 | $575.00 – $575.00 | 28 | Sep 15, 2026, contract 77-0654-184 ↗ |
| Type a sign, sheet aluminum | square foot | $25.00 | $21.50 – $30.00 | 27 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Engineering Fabric | square yard | $4.00 | $3.00 – $5.00 | 26 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Perforated square steel tube post | linear foot | $21.00 | $17.12 – $25.00 | 26 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Modified Subbase | cubic yard | $60.10 | $51.26 – $65.00 | 25 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Temporary Barrier Rail, Concrete | linear foot | $17.00 | $10.66 – $22.00 | 25 | Jul 28, 2026, contract 77-0352-490 ↗ |
| Perimeter and slope sediment control device, 12 in. diameter. | linear foot | $3.00 | $2.45 – $3.51 | 24 | Jul 28, 2026, contract 77-0352-490 ↗ |
| Remove Storm Sewer Pipe Less Than or Equal to 36 in. | linear foot | $28.25 | $24.50 – $39.62 | 24 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Shoulder Construction, Earth | station | $378.00 | $310.00 – $605.00 | 23 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Remove of sidewalk | square yard | $12.34 | $10.00 – $23.88 | 22 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Clearing AND Grubbing | acre | $9,600 | $5,708 – $16,125 | 22 | Jul 28, 2026, contract 77-0352-490 ↗ |
| Structure concrete, bridge | cubic yard | $1,175 | $991.25 – $1,319 | 22 | Jul 28, 2026, contract 77-0352-490 ↗ |
| Detectable Warnings | square foot | $55.00 | $50.00 – $60.00 | 21 | Sep 15, 2026, contract 77-0654-184 ↗ |
| Silt Fence | linear foot | $1.60 | $1.45 – $1.85 | 21 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Sidewalk, P.C. Concrete, 6 in. | square yard | $92.75 | $80.00 – $120.00 | 21 | Sep 15, 2026, contract 77-0654-184 ↗ |
| Structure concrete (rcb culvert) | cubic yard | $1,021 | $931.00 – $1,245 | 21 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Reinforced steel, stainless steel | pound | $3.75 | $3.50 – $3.75 | 20 | Jul 28, 2026, contract 77-0352-490 ↗ |
| Stabilized Construction Entrance, EC- 303 | linear foot | $65.00 | $36.88 – $72.25 | 20 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Mulching, Bonded Fiber Matrix | acre | $3,425 | $3,000 – $4,208 | 20 | Sep 15, 2026, contract 77-0803-274 ↗ |
| Remove of intakes and utility accesses | each | $1,162 | $900.00 – $1,348 | 20 | Sep 15, 2026, contract 77-0803-274 ↗ |