Construction unit costs in Marion County, IN

Median awarded unit prices for 47 items on public projects in Marion County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Indiana › Marion County

ItemPerMedianMiddle halfWinning bidsLatest source document
Construction Sign, Type Aeach$187.50$139.05 – $232.0040Apr 15, 2026, Apr 15, 2026 letting ↗
Construction Sign, Type Beach$98.00$78.75 – $112.0032Apr 15, 2026, Apr 15, 2026 letting ↗
Barricade, Type Iii-alinear foot$17.00$14.00 – $20.0029Apr 15, 2026, Apr 15, 2026 letting ↗
Temporary Pavement Marking, Removable, 4 IN.linear foot$1.45$1.27 – $1.5827Jan 14, 2026, Jan 14, 2026 letting ↗
Road Closure Sign Assemblyeach$280.00$235.00 – $395.0025Apr 15, 2026, Apr 15, 2026 letting ↗
Construction Sign, aeach$221.65$190.00 – $305.0025May 10, 2023, May 10, 2023 letting ↗
Signal Cable, Control, Copper, 5C/14 Gaugelinear foot$4.00$3.50 – $5.0025Jan 14, 2026, Jan 14, 2026 letting ↗
Pedestrian Push Button, Apseach$1,300$1,130 – $1,53023Mar 11, 2026, Mar 11, 2026 letting ↗
Bridge deck patch, partial deepsquare foot$1.00$1.00 – $4.0022Apr 15, 2026, Apr 15, 2026 letting ↗
Temporary Traffic Barrier, Type 2linear foot$44.98$26.94 – $65.4822Apr 15, 2026, Apr 15, 2026 letting ↗
Signal Cable, Roadway Loop, Copper, 1C/14 Gaugelinear foot$1.00$0.762 – $1.5022Aug 6, 2025, Aug 6, 2025 letting ↗
Flashing Arrow Signday$18.00$14.00 – $30.0021Apr 15, 2026, Apr 15, 2026 letting ↗
Saw cut for roadway loop detector and seallinear foot$15.00$12.00 – $21.3021Aug 6, 2025, Aug 6, 2025 letting ↗
Pipe, Removelinear foot$39.39$25.00 – $70.0021Jan 14, 2026, Jan 14, 2026 letting ↗
Conduit, Steel, Galvanized, 2 IN.linear foot$46.00$32.30 – $59.2621Dec 10, 2025, Dec 10, 2025 letting ↗
Line, Thermoplastic, Solid, Yellow, 4 IN.linear foot$0.94$0.75 – $1.2621Jan 14, 2026, Jan 14, 2026 letting ↗
Joint Adhesive, Surfacelinear foot$1.00$0.5 – $1.4720Mar 12, 2025, Mar 12, 2025 letting ↗
Guardrail, MGS W-beam, 6 FT 3 IN. Spacinglinear foot$25.00$23.90 – $28.1220Dec 10, 2025, Dec 10, 2025 letting ↗
Detour Route Marker Assemblyeach$104.00$78.75 – $226.5020Apr 15, 2026, Apr 15, 2026 letting ↗
Signal Detector Housingeach$1,975$1,350 – $2,34420Aug 6, 2025, Aug 6, 2025 letting ↗
Sign, Sheet, With Legend, 0.080 IN.square foot$35.10$30.00 – $49.0020Jan 14, 2026, Jan 14, 2026 letting ↗
Inlet, Removeeach$778.79$664.96 – $928.3220Jan 14, 2026, Jan 14, 2026 letting ↗
Snowplowable Raised Pavement Markereach$55.00$37.25 – $82.2520Apr 15, 2026, Apr 15, 2026 letting ↗
Riprap, Revetmentton$90.00$66.84 – $135.0019Feb 11, 2026, Feb 11, 2026 letting ↗
Pipe, Type 2, Circular, Diameter 12 IN.linear foot$90.00$75.00 – $130.3718Jan 14, 2026, Jan 14, 2026 letting ↗
Joint Adhesive, Intermediatelinear foot$0.89$0.502 – $1.2118Aug 6, 2025, Aug 6, 2025 letting ↗
Curb, Concretelinear foot$68.32$43.70 – $137.5018Mar 11, 2026, Mar 11, 2026 letting ↗
Portable Changeable Message Signeach$4,675$3,500 – $6,50017Apr 15, 2026, Apr 15, 2026 letting ↗
Line, Removelinear foot$0.78$0.6 – $1.0517Mar 11, 2026, Mar 11, 2026 letting ↗
Temporary Pavement Marking, Removable, 6 IN.linear foot$2.25$2.00 – $2.9517Apr 15, 2026, Apr 15, 2026 letting ↗
Energy Absorbing Terminal, Cz, TL-3each$6,902$5,999 – $10,12016Apr 15, 2026, Apr 15, 2026 letting ↗
Sign Post, Square, Type 1, Reinforced Anchor Baselinear foot$35.75$30.00 – $40.0516Jan 14, 2026, Jan 14, 2026 letting ↗
Truck Mounted Attenuatorday$1,200$575.00 – $1,68116Apr 15, 2026, Apr 15, 2026 letting ↗
Computer System Equipmenteach$1,085$919.81 – $1,67215Jan 14, 2026, Jan 14, 2026 letting ↗
Grooving for pavement markinglinear foot$0.75$0.445 – $0.9515Apr 15, 2026, Apr 15, 2026 letting ↗
Transverse Marking, Thermoplastic, Stop Line, White, 24 IN.linear foot$10.25$9.61 – $13.6115Mar 11, 2026, Mar 11, 2026 letting ↗
Guardrail, Removelinear foot$5.00$4.25 – $8.0514Dec 10, 2025, Dec 10, 2025 letting ↗
Sign, Sheet, With Legend, 0.100 IN.square foot$34.50$32.00 – $45.2414Aug 6, 2025, Aug 6, 2025 letting ↗
Curb AND Gutter, Concretelinear foot$43.86$31.69 – $59.5014Mar 11, 2026, Mar 11, 2026 letting ↗
Casting, Manhole, Adjust to Gradeeach$1,083$787.30 – $1,32414Feb 11, 2026, Feb 11, 2026 letting ↗
Casting, Inlet, Adjust to Gradeeach$1,033$718.75 – $1,14214Aug 6, 2025, Aug 6, 2025 letting ↗
D-1 Contraction Jointlinear foot$20.00$16.00 – $35.5913Apr 15, 2026, Apr 15, 2026 letting ↗
Law Enforcement Officerhour$60.00$60.00 – $60.0013Apr 15, 2026, Apr 15, 2026 letting ↗
Compaction aggregate no. 53ton$50.95$46.69 – $75.8112Jan 14, 2026, Jan 14, 2026 letting ↗
Field Drilled Hole in Concreteeach$22.00$18.14 – $46.4912Apr 15, 2026, Apr 15, 2026 letting ↗
Reinforced bars, epoxy coatedpound$1.54$1.50 – $1.8912Apr 15, 2026, Apr 15, 2026 letting ↗
Transverse Marking, Thermoplastic, Crosswalk Line, White, 24 IN.linear foot$10.25$9.78 – $12.4812Feb 26, 2025, Feb 26, 2025 letting ↗