Other · awarded bid prices · Williamson County
Raised reflective pavement mkr: cost per each in Williamson County, IL
Listed by the agency as “Raised Refl Pavt Mkr”.
The median awarded price is $50.00 per each, from 20 winning bids on 20 public projects in Williamson County, IL (2023–2026). Half of the awarded prices fall between $46.63 and $53.03.
Cost by state › Illinois › Williamson County › Raised Refl Pavt Mkr
Winning bids only, as printed in the agencies' bid tabulations (IDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $35.59 in 2019 to $50.00 in 2025 (+40%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2019 | $35.59 | 6 |
| 2023 | $47.00 | 7 |
| 2024 | $49.77 | 10 |
| 2025 | $50.00 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jul 31, 2026 | IDOT | 117 EACH | $54.00 | Open bid tab, 99775 ↗ |
| Apr 24, 2026 | IDOT | 32 EACH | $117.00 | Open bid tab, 99761 ↗ |
| Feb 27, 2026 | IDOT | 129 EACH | $48.00 | Open bid tab, 78B58 ↗ |
| Aug 1, 2025 | IDOT | 670 EACH | $37.61 | Open bid tab, 78A74 ↗ |
| Jun 13, 2025 | IDOT | 123 EACH | $52.71 | Open bid tab, 78B31 ↗ |
The same item across Illinois: statewide figures. See every awarded price for this item on the Raised Refl Pavt Mkr item page.
Related items in Williamson County
- Short Term Pavt Mking: $1.90 per linear foot
- Bit Matls Tack Ct: $0.01 per pound
- Temporary Ramp: $24.23 per square yard
- Raised Ref Pvt Mk Rem: $13.00 per each
- Temp Pvt Mk Line 4 - Paint: $0.01 per linear foot