Construction unit costs in Idaho

Median awarded unit prices for the 24 most-bid items on Idaho public projects, from winning bids in agency bid tabulations.

Cost by state › Idaho

ItemPerMedianMiddle halfWinning bids
Longitudinal Pavement Marking - Waterbornelinear foot$0.2$0.15 – $0.3571
Temporary Traffic Control Signssquare foot$7.00$5.49 – $12.1560
Temporary Traffic Control Maintenancehour$60.00$50.00 – $70.5052
CSS-1 Diluted Emulsified Asphalt FOR Tack Coatgallon$3.30$1.50 – $4.3851
Drumseach$11.00$9.29 – $30.0051
Excavationcubic yard$19.10$15.57 – $24.6244
Portable Changeable Message Sign (pcms)day$65.85$50.00 – $75.0644
Weighted Base Tubular Markerseach$7.50$4.58 – $13.0543
3/4" Aggregate Type B FOR Baseton$32.95$25.00 – $45.5040
Flagger Controlhour$58.38$49.00 – $64.0040
Barricade Type 3each$61.25$50.12 – $92.0038
Fiber Wattlelinear foot$3.75$3.00 – $5.0035
Removal of Signeach$150.00$100.00 – $200.0033
Inlet Protectioneach$100.00$84.50 – $157.5031
Transverse, Word, Symbol, AND Arrow Pavement Markings - Preformed Thermoplasticsquare foot$13.00$9.12 – $16.2731
Approacheach$2,160$1,200 – $3,00029
Superpave HMA Pavement Including Asphalt & Additives Class SP-3ton$145.00$115.00 – $178.7729
Sign Type B-1square foot$33.50$24.50 – $45.2528
Cold Millingsquare yard$4.08$2.38 – $9.8628
W-beam Guardraillinear foot$28.00$24.00 – $36.0025
Adjust Manhole Coverseach$1,140$910.00 – $1,60021
Granular Subbaseton$24.00$16.60 – $34.5021
Removal of Guardraillinear foot$2.33$2.00 – $5.0420
Removal OF Curb & Gutterlinear foot$5.00$4.40 – $10.0020