The median awarded price is $40.00 per linear foot, from 321 winning bids on 321 public projects in California (2023–2026). Half of the awarded prices fall between $24.50 and $60.00.
Cost by state › California › Temporary Barrier System
$40.00median per linear foot
$24.50 – $60.00middle half (25th–75th percentile)
321winning bids, 321 source documents
2023–2026lettings covered (last 3 years)
Winning bids only, as printed in the agencies' bid tabulations (Caltrans). These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $30.00 in 2022 to $28.72 in 2026 (-4%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2022 | $30.00 | 58 |
| 2023 | $35.00 | 136 |
| 2024 | $42.00 | 150 |
| 2025 | $35.00 | 114 |
| 2026 | $28.72 | 44 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Sep 17, 2026 | Caltrans | 11200 LF | $14.41 | contract 04-0W0504 ↗ |
| Sep 16, 2026 | Caltrans | 3320 LF | $27.44 | contract 03-0N4504 ↗ |
| Sep 3, 2026 | Caltrans | 320 LF | $155.15 | contract 10-1H5604 ↗ |
| Sep 3, 2026 | Caltrans | 6440 LF | $15.00 | contract 03-4J9004 ↗ |
| Sep 1, 2026 | Caltrans | 4970 LF | $16.00 | contract 04-0W0604 ↗ |
See every awarded price for this item, in all states, on the Temporary Barrier System item page.
Related items in California
- Treated Wood Waste: $1.00 per pound
- Miscellaneous Iron and Steel: $5.00 per pound
- Compost (Cy): $103.75 per cubic yard
- Shoulder Backing: $83.06 per ton
- Structural Steel: $20.00 per pound