Traffic · awarded bid prices · Los Angeles County
Remove Sign Post: cost per each in Los Angeles County, CA
The median awarded price is $107.00 per each, from 22 winning bids on 22 public projects in Los Angeles County, CA (2021–2026). Half of the awarded prices fall between $88.50 and $141.25.
Cost by state › California › Los Angeles County › Remove Sign Post
Winning bids only, as printed in the agencies' bid tabulations (Los Angeles County Flood Control District, Los Angeles County Public Works). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $107.00 in 2023 to $145.00 in 2025 (+36%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2023 | $107.00 | 7 |
| 2025 | $145.00 | 5 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 18, 2026 | Los Angeles County Public Works | 1 EA | $90.00 | Open bid tab, contract TSM0010252 ↗ |
| Jul 14, 2026 | Los Angeles County Public Works | 8 EA | $55.00 | Open bid tab, contract RMD1102001 ↗ |
| Feb 3, 2026 | Los Angeles County Public Works | 39 EA | $55.50 | Open bid tab, contract RDC0015749 ↗ |
| Nov 18, 2025 | Los Angeles County Public Works | 1 EA | $145.00 | Open bid tab, contract TSM0010460 ↗ |
| Oct 28, 2025 | Los Angeles County Public Works | 3 EA | $90.00 | Open bid tab, contract RDC0016428 ↗ |
See every awarded price for this item on the Remove Sign Post item page.
Related items in Los Angeles County
- Detectable Warning Surface: $69.00 per square foot
- Changeable Message Sign: $2,602 per each
- 12-Conductor Signal Cable(Excluding Conduit): $7.00 per linear foot
- 3-Conductor Signal Cable(Excluding Conduit): $3.75 per linear foot
- 2-Pair Detector Lead-In Cable: $3.00 per linear foot
- Inductive Loop Detector And Leads Saw Cut: $17.00 per linear foot
- 5-Conductor Signal Cable(Excluding Conduit): $4.75 per linear foot
- Pavement Markings (Thermoplastic): $12.00 per square foot