Other · awarded bid prices · Jefferson County
Remove pipe: cost per linear foot in Jefferson County, AL
Listed by the agency as “Removing Pipe”.
The median awarded price is $37.63 per linear foot, from 15 winning bids on 15 public projects in Jefferson County, AL (2024–2026). Half of the awarded prices fall between $22.88 and $75.00.
Cost by state › Alabama › Jefferson County › Removing Pipe
Winning bids only, as printed in the agencies' bid tabulations (ALDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $37.63 in 2024 to $26.46 in 2025 (-30%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2024 | $37.63 | 5 |
| 2025 | $26.46 | 7 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jul 31, 2026 | ALDOT | 936 LF | $20.00 | Open bid tab, contract 20260731001 |
| May 29, 2026 | ALDOT | 34 LF | $138.58 | Open bid tab, contract 20260529023 |
| Feb 27, 2026 | ALDOT | 588 LF | $50.00 | Open bid tab, contract 20260227001 |
| Nov 7, 2025 | ALDOT | 194 LF | $94.50 | Open bid tab, contract 20251107053 |
| Aug 29, 2025 | ALDOT | 1095 LF | $26.46 | Open bid tab, contract 20250829022 |
See every awarded price for this item on the Removing Pipe item page.
Related items in Jefferson County
- Wattle: $11.57 per linear foot
- Material Remixing Device: $36,284 per each
- Cones (36 Inches High): $28.31 per each
- Filter Blanket, Geotextile: $5.56 per square yard
- Temporary Mulching: $600.62 per ton
- Sand Bags: $10.00 per each