Skip to content
Hubstake

Agency · awarded bid prices

Southeast Regional Management District: awarded unit prices

37 winning bid prices read from 1 source documents, 2026. The table lists the 37 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Southeast Regional Management District

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Onsite Dust Control, Contractor To Obtain A Water Meter From Texas Water Utilities, L.P. And Water The Site As Needed To Prevent Any Blowing Dust For The Duration Of The Project, Contractor Is Responsible For The Cost Associated With Meter And Purchasing Of The Water From Texas Water Utilites, L.P., Complete In Placeday1—$500.00$500.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Additional Clearing And Grubbing, Includes Root Raking And Back Dragging, And Offsite Disposal Of Cleared And Grubbed Material, (As Directed By Engineer), Complete In Placeacre1—$9,500$9,500Aug 18, 2026, Open bid tab, 6969-1640 ↗
Monthly Detention Pond Maintenance, Includes Watering Via Water Truck, Reseeding, Regrading Of Reels As Needed, (Minimum 3 Months) (As Directed B Y Engineer), Complete In Placemonth1—$1,000$1,000Aug 18, 2026, Open bid tab, 6969-1640 ↗
Soil Amendment Profile Allowance (Includes Up To The Following: Application Rate Of 5,000 Lb/Ac Soil Media Such As Progranics, Probitiocs, Organix Biotic, Or Equivalent), Gypsum At Application Rate Of 2,500 Lb/Ac, Slow Release Nitrogen Product At Application Rate Of 160 Lb/Ac, Liquid Stimulants At Application Rate Of 5 Gal/Ac, And Ph Adjustments Within 2.5 Points), As Directed By Engineer And When Authorized By Owner, Complete In Placesquare yard1—$1.75$1.75Aug 18, 2026, Open bid tab, 6969-1640 ↗
Hydraulic seeding of detention pond side slopes/backslope swales & reserves: including (warm season) seeding of 65# hulled bermuda, 125# millet (foxtail / browntop / (proso), 500# 13-13-13 fertilizer and applicable mulching product relevant to slope structure; soil testing, and soil amendments to obtain favorable soil condition, complete in place. hydraulic mulching application rates (based on slope) are as follows: >4h:1v and =3h:1v; 3,500 lb/ac high performance fgmsquare yard1—$1.35$1.35Aug 18, 2026, Open bid tab, 6969-1640 ↗
Broadcast Seeding Of Detention Pond Bottoms, March - October (Warm Season), 50# Hulled Bermuda, 100# Millet (Foxtail / Browntop / (Proso), 500# 13-13-13 Fertilizeracre1—$10.00$10.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Broadcast seeding of right of way or reserves, march - october (warm season), 50# hulled bermuda, 100# millet (foxtail / browntop / (proso), 500# 13-13-13 fertilizeracre1—$10.00$10.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Extra Cement Stabilized Sand Backfill (2.0 Sacks Per Ton), (To Be Used As Directed By The Engineer), Complete In Placecubic yard1—$10.00$10.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Additional cost to scarify fill areas to receive fill to deep of 24 inches to aerate the subgrade soils and re-compaction to 95% standard proctor density ( to be used only at the direction of the engineer), complete in placeacre1—$50.00$50.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Additional cost to scarify fill areas to receive fill to deep of 12 inches to aerate the subgrade soils and re-compaction to 95% standard proctor density ( to be used only at the direction of the engineer), complete in placeacre1—$50.00$50.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Over Excavation Of Unsuitable Material Prior To Fill Placement Within Fill Areas, Includes Excavation, Demucking, Spreading Of Unsuitable Material, And Placement Of Material As Final Lift Upon Completion Of Fill (As Directed By The Engineer And To Be Surveyed And Verified Before Final Payment), Complete In Placecubic yard1—$0.5$0.5Aug 18, 2026, Open bid tab, 6969-1640 ↗
Method "A" Construction Staking By Contractor, Contractor To Use Lja Surveying, Inc. For Construction Staking, To Include Staking At 100' Intervals For The Fill Of Future Sections As Outlined In This Bid Proposal. Any Restaking Required Regardless Of The Reason Will Be Charged To The Contractors On A Time And Materials Basis And Is Separate From This Contract, Complete In Placels1—$10,000$10,000Aug 18, 2026, Open bid tab, 6969-1640 ↗
Detention Basin And Fill As-Built Surveying, (As Per Lja Surveying, Inc.), Complete In Placels1—$15,000$15,000Aug 18, 2026, Open bid tab, 6969-1640 ↗
Method "A" Construction Staking By The Contractor, Contractor To Use Lja Surveying, Inc. For Construction Staking, To Include Staking For The High Bank, Toe, Overflow Swale, Storm Sewer, Outfalls, And Slope Paving As Outlined In This Bid Proposal. Any Restaking Required Regardless Of The Reason Will Be Charged To The Contractors On A Time And Materials Basis And Is Separate From This Contract, Complete In Placels1—$12,000$12,000Aug 18, 2026, Open bid tab, 6969-1640 ↗
Maintain Existing Stabilized Construction Exit, Complete In Placeeach1—$1,000$1,000Aug 18, 2026, Open bid tab, 6969-1640 ↗
Outfall Structure, Includes Slope Pavement, Timber Bent (As Necessary), Cut Pipe Flush With Slope Pavement, And All Appurtenances, All Sizes, All Depths, Complete In Placeeach1—$5,550$5,550Aug 18, 2026, Open bid tab, 6969-1640 ↗
5 inch reinforced concrete pilot channel, complete in placesquare yard1—$115.00$115.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Backslope interceptor and outfall structure, includes 18 inch cgmp, interceptor structure, and slope protection, complete in placeeach1—$10,500$10,500Aug 18, 2026, Open bid tab, 6969-1640 ↗
5' X 3' Reinforced Concrete Box Culvert, Astm C-1577, Includes Bedding And Backfill, All Depths, Complete In Placelinear foot1—$385.16$385.16Aug 18, 2026, Open bid tab, 6969-1640 ↗
Bypass Pumping Of Water From Temporary Coffer Dam Into Existing Tributary, 24 Hrs. (As Directed By Engineer), Complete In Placeday1—$100.00$100.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Construction and remove of temporary coffer dam for the construction of culvert crossing, includes dewatering and all appurtenances (as directed by the engineer), all sizes, all depths, complete in placeeach1—$500.00$500.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Install and remove of low water crossing during duration of the project, includes two 36 inch cgmp, remove and disposal of cgmp and restoring the site and slopes back to original condition or better, compelte in placeeach1—$2,500$2,500Aug 18, 2026, Open bid tab, 6969-1640 ↗
Drainage Swales, As Directed By Engineer, Complete In Placelinear foot1—$0.85$0.85Aug 18, 2026, Open bid tab, 6969-1640 ↗
Import fill, includes haul from designated stockpile, using off road trucks, (0.5 - 1 mile), placement and compaction to 95% standard proctor density, with maximum 8 inch lifts, and final site grading, (as directed by engineer), complete in placecubic yard1—$2.27$2.27Aug 18, 2026, Open bid tab, 6969-1640 ↗
Right Of Way Excavation Includes Hauling Excavated Material To Designated Fill Areas Onsite Using Off Road Trucks, (0.0-0.5 Mile), Stripping, Stockpiling Strippings, Placement And Compaction To +95% Standard Proctor Density, With Maximum 8'' Lifts, And Re- Application Of Stripping To Final Graded Area, Complete In Placecubic yard1—$2.27$2.27Aug 18, 2026, Open bid tab, 6969-1640 ↗
Pond Excavation Includes Hauling Excavated Material To Designated Fill Areas Onsite Using Off Road Trucks (0.5-1 Mile), Includes Stripping, Stockpiling Strippings, Placement And Compaction To +95% Standard Proctor Density, With Maximum 8'' Lifts, And Re-Application Of Stripping To Final Graded Area, Complete In Placecubic yard1—$2.27$2.27Aug 18, 2026, Open bid tab, 6969-1640 ↗
Utility spoils, includes hauling excavated material onsite, includes stripping, stockpiling strippings, placement and compaction to 95% standard proctor density, with maximum 8 inch lifts, final grading, and re-application of strippings, complete in placecubic yard1—$2.00$2.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
8 inch brick plug, all sizes, all depths, complete in placeeach1—$50.00$50.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
54 inch reinforced concrete pipe storm sewer, astm c-76, class iii, includes bedding and backfill, all depths, complete in placelinear foot1—$342.05$342.05Aug 18, 2026, Open bid tab, 6969-1640 ↗
Reinforced concrete type "c" manhole for 48 inch storm sewer and larger with reinforced concrete type "e" inlet top, all sides open, includes adjustments, all depths, complete in placeeach1—$5,150$5,150Aug 18, 2026, Open bid tab, 6969-1640 ↗
Dewatering For Storm Sewer, (As Directed By Engineer), All Sizes, All Depths, Complete In Placelinear foot1—$1.00$1.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Storm Water Pollution Prevention Plan Compliance, Includes General Source Controls And All Items Not Specifically Listed In The Bid Proposal, Complete In Placels1—$3,500$3,500Aug 18, 2026, Open bid tab, 6969-1640 ↗
Install, Maintain, And Remove Concrete Truck Washout Area, Complete In Placeeach1—$100.00$100.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
18 inch thick concrete rip rap, includes geotextile fabric, complete in placesquare yard1—$124.75$124.75Aug 18, 2026, Open bid tab, 6969-1640 ↗
4 inch reinforced concrete slope pavement with toe walls all around, complete in placesquare yard1—$115.00$115.00Aug 18, 2026, Open bid tab, 6969-1640 ↗
Trench Safety System For Storm Sewer, All Sizes, All Depths, Complete In Placelinear foot1—$0.1$0.1Aug 18, 2026, Open bid tab, 6969-1640 ↗
Backslope interceptor swale, includes excavation, stripping, stockpiling strippings, placement and compaction to 95% standard proctor density, with maximum 8 inch lifts, and re- application of strippings, complete in placelinear foot1—$0.85$0.85Aug 18, 2026, Open bid tab, 6969-1640 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Texas: statewide figures.