| Implementation Of Bmps | ls | 195 | $5,000 | $625,000 | $10.00 – $625,000 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Mobilization | ls | 172 | — | $2,430,000 | $1.00 – $3,998,042 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Office Facilities | ls | 96 | $5,000 | $8,058 | $500.00 – $66,180 | May 3, 2016, Open bid tab, contract FCC0001236 ↗ |
| Traffic Control | ls | 96 | — | $1,279,000 | $100.00 – $1,279,000 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Clearing and Grubbing | ls | 71 | — | $35,000 | $500.00 – $502,550 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Unclassified Excavation | cubic yard | 69 | $45.00 | $33.00 | $3.00 – $875.43 | May 12, 2026, Open bid tab, contract FCC0001409 ↗ |
| Electrical Work | ls | 58 | — | $11,000 | $10,000 – $1,425,000 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Shoring Of Open Excavatio | ls | 57 | — | $8,325 | $500.00 – $2,396,903 | Jun 16, 2009, Open bid tab, contract FCC0001110 ↗ |
| Ac Pavement | ton | 55 | $120.00 | $220.00 | $43.00 – $1,089 | May 12, 2026, Open bid tab, contract FCC0001409 ↗ |
| Catch basin per standard plan 30 | each | 55 | $5,800 | $5,750 | $3,900 – $20,000 | May 5, 2009, Open bid tab, contract FCC0001075 ↗ |
| Restoration Of Existing Im | ls | 54 | $7,925 | $15,000 | $500.00 – $420,000 | May 5, 2009, Open bid tab, contract FCC0001075 ↗ |
| Shoring Of Open Excavations | ls | 51 | — | $55,600 | $10.00 – $3,220,000 | Jan 13, 2026, Open bid tab, contract FCC0001401 ↗ |
| Office Facilities | mth | 45 | $4,000 | $4,500 | $500.00 – $20,000 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Construction Schedule (As-Built) (Stipulated Unit Price Of $1,000) | ls | 41 | $1,000 | $1,000 | $1,000 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Construction Schedule (Update) (Stipulated Unit Price Of $500/Month) | mth | 41 | $500.00 | $500.00 | $500.00 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Concrete remove (reinforced) | cubic yard | 38 | $500.00 | $650.00 | $80.00 – $6,580 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Crushed Miscellaneous Base | cubic yard | 37 | $70.00 | $105.00 | $22.00 – $755.40 | May 12, 2026, Open bid tab, contract FCC0001409 ↗ |
| Unclassified Fill | cubic yard | 36 | $35.00 | $75.00 | $0.25 – $600.00 | Jun 20, 2023, Open bid tab, contract FCC0001218 ↗ |
| Restoration Of Permanent | ls | 36 | — | $227,328 | $2,000 – $1,350,000 | Jun 16, 2009, Open bid tab, contract FCC0001110 ↗ |
| 18 inch reinforced concrete pipe, 2000 d | linear foot | 31 | $150.00 | $265.00 | $50.00 – $737.00 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Junction Structure Per St | each | 31 | $3,000 | $2,497 | $800.00 – $7,484 | Jun 16, 2009, Open bid tab, contract FCC0001110 ↗ |
| Implementation Of The Ltwhp | ls | 28 | — | $50,000 | $500.00 – $115,000 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Concrete remove (reinfo | cubic yard | 24 | $375.00 | $66.50 | $60.00 – $3,480 | May 12, 2009, Open bid tab, contract FCC0001097 ↗ |
| Manhole per standard plan 320 | each | 24 | $6,500 | $20,000 | $3,000 – $425,000 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Bar reinforced steel | pound | 24 | $2.50 | $1.40 | $0.85 – $18.10 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Structure Concrete | cubic yard | 23 | $1,700 | $3,200 | $290.00 – $11,000 | May 12, 2026, Open bid tab, contract FCC0001409 ↗ |
| Implementation Of The Site-Specific Health And Safety Plan | ls | 22 | $12,188 | $100,000 | $2,500 – $100,000 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Miscellaneous Mechanical Work | ls | 22 | $48,066 | $200,000 | $2,095 – $606,000 | May 24, 2022, Open bid tab, contract FCC0001277 ↗ |
| Transition Structure Per | each | 22 | $11,250 | $12,500 | $4,000 – $80,000 | May 5, 2009, Open bid tab, contract FCC0001075 ↗ |
| Chain Link Fence, 5' High | linear foot | 22 | $36.50 | $110.00 | $9.50 – $200.00 | Apr 13, 2021, Open bid tab, contract FCC0001315 ↗ |
| Restoration Of Existing Improvements | ls | 21 | — | $30,000 | $500.00 – $155,000 | May 11, 2021, Open bid tab, contract FCC0001332 ↗ |
| Concrete remove (non- reinforced) | cubic yard | 21 | $350.00 | $1,500 | $35.00 – $2,638 | May 12, 2026, Open bid tab, contract FCC0001409 ↗ |
| Implementation Of The Swppp | ls | 20 | $35,000 | $324,000 | $2,000 – $324,000 | May 15, 2025, Open bid tab, contract FCC0001272 ↗ |
| Construction Schedule (Baseline) (Stipulated Unit Price Of $5,000) | ls | 19 | $5,000 | $5,000 | $5,000 | May 24, 2022, Open bid tab, contract FCC0001277 ↗ |
| Operational Tests | ls | 19 | — | $20,000 | $1,000 – $60,000 | May 12, 2026, Open bid tab, contract FCC0001409 ↗ |
| Remove Existing Chain Link Fence | linear foot | 19 | $10.00 | $50.00 | $3.00 – $233.34 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| Restoration Of Permanent Surfacing | ls | 18 | $23,150 | $40,000 | $6,000 – $200,000 | May 19, 2026, Open bid tab, contract FCC0001341 ↗ |
| 24 inch reinforced concrete pipe, 2000 d | linear foot | 18 | $158.50 | $120.00 | $100.00 – $1,300 | Apr 13, 2021, Open bid tab, contract FCC0001290 ↗ |
| Manhole per standard plan 321 | each | 18 | $5,700 | $3,500 | $3,300 – $10,000 | Mar 20, 2012, Open bid tab, contract FCC0001213 ↗ |
| Saw Cut Concrete | linear foot | 18 | — | $20.00 | $1.00 – $183.35 | Jan 12, 2021, Open bid tab, contract FCC0001307 ↗ |