| 24 inch reinforced concrete pipe storm sewer, astm c-76, class iii, includes bedding and backfill, all depths, complete in place | linear foot | 2 | — | $82.00 | $66.00 – $82.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Extra Surveying Trip For Restaking Previously Provided Construction Stakes That Were Destroyed By Others (This Item Does Not Include Restaking Due To Contractor Destroying Own Construction Staking Or Failing To Protect Construction Staking From Known Hazards Such As Construction Traffic, Ordering Staking Too Far In Advance, Or Contractor'S Own Equipment, Etc.) | day | 1 | — | $2,500 | $2,500 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Full Construction Staking For Water And Drainage Facilities And Paving And Appurtenances Coordinate With Lja, Inc., Clayton Gafford, 713.271.0561, Complete In Place | ls | 1 | — | $37,000 | $37,000 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| City Of Needville Construction Permit | ls | 1 | — | $35,000 | $35,000 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Demuck and fill existing centerline drainage swale, placement and compaction to 95% standard proctor density, with maximum 8 inch lifts, complete in place | linear foot | 1 | — | $0.18 | $0.18 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Dual 6 inch pvc irrigation sleeve, schedule 40, includes risers, pvc end cap, cement stabilized sand backfill and markers, complete in place | linear foot | 1 | — | $40.00 | $40.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Dual 4 inch pvc irrigation sleeve, schedule 40, includes risers, pvc end cap, cement stabilized sand backfill and markers, complete in place | linear foot | 1 | — | $18.00 | $18.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 6:1 safety end treatment for 24 inch storm sewer, includes slope paving, complete in place | each | 1 | — | $2,460 | $2,460 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 18 inch reinforced concrete pipe storm sewer, astm c-76, class iii, includes bedding and backfill, all depths, complete in place | linear foot | 1 | — | $63.00 | $63.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 6:1 safety end treatment for 18 inch storm sewer, includes slope paving, complete in place | each | 1 | — | $1,500 | $1,500 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 4 inch square double reflectorized blue traffic buttons for fire hydrant locations, complete in place | each | 1 | — | $18.00 | $18.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 2' Sawcut, Remove And Offsite Disposal Of Existing Asphalt Pavement, Expose, Clean, And Tie-In Existing Asphalt Pavement To Proposed Asphalt Pavement, Complete In Place | linear foot | 1 | — | $15.00 | $15.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Type 7 ada ramp, includes truncated dome pavers with contrasting color per deatil, complete in place | each | 1 | — | $1,300 | $1,300 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Final Grading Of Right-Of-Way, Complete In Place | ls | 1 | — | $12,000 | $12,000 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 3 inch type "d" hmac paving with 8 inch black base and prime coat, complete in place | square yard | 1 | — | $155.00 | $155.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Fly ash for 8 inch stabilized subgrade preparation, 7% by dry weight, as required by soil conditions and approved by geotechnical engineer, complete in place | ton | 1 | — | $1.00 | $1.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Hydrated lime for 8 inch stabilized subgrade preparation, 8% by dry weight, as required by soil conditions and approved by geotechnical engineer, complete in place | ton | 1 | — | $368.00 | $368.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 8 inch stabilized subgrade manipulation, complete in place | square yard | 1 | — | $5.68 | $5.68 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Additional Cost For Storm Sewer Bedding For Unsatisfactory Soil Conditions, (As Directed By Engineer), Complete In Place | linear foot | 1 | — | $15.00 | $15.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Remove existing reinforced concrete type "e" inlet top and replace with type "c" storm manhole top, for 48 inch storm sewer and larger , all depths, complete in place | each | 1 | — | $2,322 | $2,322 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Remove and offsite disposal of existing 8 inch brick plug and connect proposed storm sewer, all sizes, all depths, complete in place | each | 1 | — | $8.00 | $8.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Standard Reinforced Concrete Precast Type "D" Inlet, Includes Inlet Protection Barrier, All Depths, Complete In Place | each | 1 | — | $3,000 | $3,000 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Stage 2 - Reinforced Concrete Type "C" Inlet With Grate Top, All Depths, Complete In Place | each | 1 | — | $1,800 | $1,800 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Stage 1 - Reinforced Concrete Type "C" Inlet With Grate Top, Includes Inlet Protection Barrier For Stage 1 Inlet, All Depths, Complete In Place | each | 1 | — | $1,250 | $1,250 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Reinforced Concrete Storm Sewer Bend, With Type "C" Storm Manhole Top, As Shown In Plans, Complete In Place | each | 1 | — | $4,150 | $4,150 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 7' X 6' Reinforced Concrete Box Culvert, Astm C-1433, Includes Bedding And Backfill, All Depths, Complete In Place | linear foot | 1 | — | $548.00 | $548.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 12 inch plug & clamp with 2 inch blow-off valve & box assembly, complete in place | each | 1 | — | $800.00 | $800.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 12 inch pvc restrained joint water line, c-900, dr 14, class 305, includes restrained joint fitting, bedding and backfill, all depths, complete in place | linear foot | 1 | — | $202.00 | $202.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Utility spoils, includes hauling excavated material onsite, includes stripping, stockpiling strippings, placement and compaction to 95% standard proctor density, with maximum 8 inch lifts, final grading, and re-application of strippings, complete in place | ls | 1 | — | $8.00 | $8.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Video Inspection Of Storm Sewer, All Sizes, Includes Digital Copy, Complete In Place | linear foot | 1 | — | $1.00 | $1.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 8 inch brick plug, all sizes, all depths, complete in place | each | 1 | — | $100.00 | $100.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 48 inch reinforced concrete pipe storm sewer, astm c-76, class iii, includes bedding and backfill, all depths, complete in place | linear foot | 1 | — | $185.00 | $185.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 8 inch plug & clamp with 2” blow-off valve & box assembly, complete in place | each | 1 | — | $717.00 | $717.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Wet connection of proposed 12 inch water line to existing water line, includes fitting, all adapters and connectors necessary, and remove of existing plug & clamp and 2 inch blow-off valve & box, all depths, complete in place | each | 1 | — | $980.11 | $980.11 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 12 inch awwa gate valve & box, complete in place | each | 1 | — | $3,495 | $3,495 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 12 inch pvc water line, c-900, dr 18, class 235, includes fitting, bedding and backfill, all depths, complete in place | linear foot | 1 | — | $48.00 | $48.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| Inlet Protection Barrier For Stage Ii Inlet, Complete In Place | each | 1 | — | $1.00 | $1.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 54 inch reinforced concrete pipe storm sewer, astm c-76, class iii, includes bedding and backfill, all depths, complete in place | linear foot | 1 | — | $280.00 | $280.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 36 inch reinforced concrete pipe storm sewer, astm c-76, class iii, includes bedding and backfill, all depths, complete in place | linear foot | 1 | — | $131.00 | $131.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |
| 4 inch pvc irrigation sleeve, schedule 40, includes risers, pvc end cap, cement stabilized sand backfill and markers, complete in place | linear foot | 1 | — | $12.00 | $12.00 | Nov 12, 2026, Open bid tab, 2025-4205 ↗ |