| Unclassified Excavation | cubic yard | 52 | $126.50 | $17.00 | $17.00 – $540.00 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Construction Permit | ls | 42 | $10,100 | $10,000 | $5,200 – $45,700 | Nov 10, 2025, Open bid tab, 24-6053 ↗ |
| Signing and stripe | ls | 37 | — | $158,310 | $3,866 – $347,430 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Project Advertisement Sign | each | 37 | $2,000 | $2,300 | $750.00 – $5,000 | Aug 27, 2025, Open bid tab, 25-2604 ↗ |
| PCC Curb Ramp | square foot | 28 | $18.50 | $49.00 | $5.25 – $68.00 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Ac Pavement | ton | 25 | $120.00 | $256.00 | $74.00 – $400.00 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Root Shave* | each | 24 | $525.00 | $7,000 | $250.00 – $7,000 | Jun 4, 2024, Open bid tab, 22-9001 ↗ |
| Labor Agreement Oversight | ls | 24 | $10,000 | $15,000 | $5,000 – $25,000 | Feb 2, 2021, Open bid tab, 14-6802, 18-6424, 20-6618 ↗ |
| Pcc sidewalk (t=4 inch) | square foot | 22 | $13.00 | $18.00 | $5.00 – $50.00 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| As-built Plans | ls | 18 | $5,000 | $2,500 | $2,500 – $50,000 | Jan 13, 2026, Open bid tab, 26-6012 ↗ |
| Cold milling (2 inch) | square foot | 17 | $0.35 | $0.7 | $0.17 – $5.00 | Jun 29, 2023, Open bid tab, 22-6989 ↗ |
| PCC Curb and Gutter (Type A-2-8)* | linear foot | 14 | $70.50 | $153.00 | $30.00 – $153.00 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Asphalt Rubber Hot Mix (ARHM) | ton | 14 | $123.50 | $147.18 | $85.00 – $275.00 | Jul 3, 2024, Open bid tab, 23-6702 ↗ |
| P.c.c. sidewalk, 4 inch | square foot | 14 | $8.80 | $15.00 | $5.25 – $17.50 | Jun 26, 2023, Open bid tab, 21-6975 ↗ |
| PCC Cross Gutter* | square foot | 12 | $21.50 | $27.00 | $15.00 – $50.00 | Apr 18, 2023, Open bid tab, 23-7543 ↗ |
| Install No. 6 Pull Box | each | 11 | $1,000 | $1,275 | $700.00 – $1,300 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Furnish and Install New #6 Pullbox | each | 9 | $1,060 | $1,320 | $543.00 – $2,360 | Jun 29, 2023, Open bid tab, 22-6989 ↗ |
| Install 3 inch pvc conduit per plan | linear foot | 9 | $56.00 | $60.00 | $40.00 – $76.00 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Install 2 inch pvc conduit per plan | linear foot | 9 | $57.00 | $75.00 | $20.53 – $75.00 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| PCC Curb and Gutter (Type A-2-6)* | linear foot | 9 | $72.00 | $80.00 | $48.00 – $231.00 | Jun 4, 2024, Open bid tab, 22-9001 ↗ |
| Rubberized Emulsion Aggregate Slurry (REAS) Type II | ton | 9 | $699.00 | $1,993 | $400.00 – $1,993 | May 2, 2023, Open bid tab, 22-6988 ↗ |
| Irrigation | ls | 9 | $142,500 | $222,500 | $10,000 – $450,000 | Jul 10, 2024, Open bid tab, 20-2731 ↗ |
| Clearing and Grubbing | ls | 9 | $30,000 | $82,500 | $10,000 – $150,000 | Jul 10, 2024, Open bid tab, 20-2731 ↗ |
| Construction Permits | ls | 8 | $9,250 | $7,000 | $4,680 – $16,500 | Jan 13, 2026, Open bid tab, 26-6012 ↗ |
| Install No. 6E Pull Box | each | 8 | $1,222 | $1,500 | $885.00 – $2,000 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| SWPPP (Risk Level 2) | ls | 8 | $41,000 | $30,000 | $8,500 – $357,000 | Jun 26, 2024, Open bid tab, 22-1381 ↗ |
| Adjust Sewer and Drainage Manhole to Finished Grade | each | 8 | $1,125 | $1,550 | $750.00 – $1,550 | Jul 3, 2024, Open bid tab, 23-6702 ↗ |
| Install 4” PVC Conduit per plan * | linear foot | 8 | $80.41 | $95.00 | $50.00 – $111.00 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Adjust Water Valve Frame and Cover to Finished Grade | each | 7 | $1,300 | $2,049 | $500.00 – $2,049 | Oct 17, 2023, Open bid tab, 22-1406 ↗ |
| Pcc Curb, Type B1 | linear foot | 7 | $40.00 | $85.00 | $31.59 – $85.00 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Asphalt Rubber Hot Mix | ton | 7 | $114.11 | $130.00 | $85.00 – $147.00 | Jun 4, 2024, Open bid tab, 22-9001 ↗ |
| Asphalt Concrete | ton | 7 | $165.00 | $165.00 | $90.00 – $190.00 | Jun 29, 2023, Open bid tab, 22-6989 ↗ |
| Crack seal | ls | 7 | $44,000 | $72,000 | $6,500 – $166,779 | Apr 18, 2023, Open bid tab, 23-6907 ↗ |
| Project Advertising Sign(s) | each | 6 | $943.50 | $550.00 | $550.00 – $1,780 | Nov 20, 2024, Open bid tab, 25-6030 ↗ |
| Furnish and Install Traffic Loops Type E † | each | 6 | $380.00 | $448.00 | $225.00 – $800.00 | Jul 3, 2024, Open bid tab, 23-6702 ↗ |
| Remove of 6 inch pcc at various locations | cubic yard | 6 | $149.00 | $172.00 | $56.00 – $172.00 | Apr 18, 2023, Open bid tab, 23-7543 ↗ |
| Construct PCC Curb Ramp* | square foot | 6 | $15.00 | $35.00 | $9.00 – $35.00 | Mar 28, 2023, Open bid tab, 22-1405 ↗ |
| Construct pcc sidewalk (t=4 inch)* | square foot | 6 | $8.00 | $10.50 | $5.00 – $10.50 | Jan 3, 2020, Open bid tab, 20-6956, 20-6437 ↗ |
| PCC Driveway Approach (T=8”) | square foot | 6 | $21.61 | $22.00 | $17.50 – $50.00 | Jul 3, 2024, Open bid tab, 23-6702 ↗ |
| Protection of Surface Utility Frames and Covers | ls | 6 | — | $50,000 | $952.00 – $50,000 | Oct 18, 2022, Open bid tab, 22-1341 ↗ |