| Mobilization | ls | 4,877 | — | $28,500 | $0.01 – $36,481,382 | Oct 15, 2026, CDOT cost lookup · contract C27332 ↗ |
| Construction traffic sign (b) | each | 4,534 | $72.00 | $5.00 | $0.26 – $4,590 | Oct 15, 2026, CDOT cost lookup · contract C27332 ↗ |
| Traffic Cone | each | 4,309 | $10.00 | $5.00 | $0.01 – $100.00 | Oct 15, 2026, CDOT cost lookup · contract C27332 ↗ |
| Flagging | hour | 4,309 | $22.04 | $24.00 | $0.01 – $150.00 | Oct 15, 2026, CDOT cost lookup · contract C27332 ↗ |
| Construction traffic sign (a) | each | 4,024 | $50.00 | $5.00 | $0.01 – $2,100 | Oct 15, 2026, CDOT cost lookup · contract C27332 ↗ |
| Sanitary Facility | each | 3,700 | $1,050 | $500.00 | $1.00 – $69,425 | Oct 15, 2026, CDOT cost lookup · contract C27332 ↗ |
| Traffic control inspection | day | 3,386 | $125.00 | $170.00 | $0.01 – $2,029 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Drum Channel DEV | each | 3,287 | $36.00 | $25.00 | $0.1 – $6,600 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Traffic control mgmt | day | 3,186 | $575.00 | $250.00 | $0.01 – $8,134 | Oct 15, 2026, CDOT cost lookup · contract C27332 ↗ |
| Construction surveying | ls | 2,784 | — | $38,000 | $250.00 – $5,789,566 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Construction traffic sign (c) | each | 2,532 | $85.00 | $78.00 | $0.26 – $1,711 | Oct 2, 2026, CDOT cost lookup · contract C27827 ↗ |
| Field lab (class 2) | each | 2,335 | $12,000 | $30,000 | $1.00 – $220,000 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Flash arrow panel (c type) | each | 2,272 | $1,123 | $250.00 | $1.00 – $16,800 | Oct 15, 2026, CDOT cost lookup · contract C27332 ↗ |
| Seeding (Native) | acre | 2,169 | $783.50 | $2,062 | $0.01 – $104,830 | Aug 27, 2026, CDOT cost lookup · contract C26972 ↗ |
| Potholing | hour | 2,168 | $200.00 | $300.00 | $1.00 – $2,300 | Oct 8, 2026, CDOT cost lookup · contract C24946 ↗ |
| Port Mesg Panel | each | 2,076 | $5,000 | $2,300 | $1.00 – $48,000 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Emul asphalt (ss) | gallon | 2,049 | $2.00 | $7.00 | $0.01 – $240.00 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Remove ground sign | each | 1,956 | $75.00 | $50.00 | $2.00 – $4,623 | Oct 8, 2026, CDOT cost lookup · contract C24946 ↗ |
| Sign panel (class i) | square foot | 1,893 | $20.00 | $22.00 | $2.00 – $550.00 | Oct 8, 2026, CDOT cost lookup · contract C24946 ↗ |
| Remove asphalt mat (milling) | square yard | 1,879 | $3.00 | $20.00 | $0.18 – $620.00 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Blading | hour | 1,873 | $115.00 | $145.00 | $1.00 – $615.35 | Oct 8, 2026, CDOT cost lookup · contract C24946 ↗ |
| Epoxy pavement marking | gallon | 1,811 | $75.30 | $300.00 | $24.50 – $3,450 | Oct 2, 2026, CDOT cost lookup · contract C27827 ↗ |
| Remove pavement marking | square foot | 1,796 | $1.65 | $2.00 | $0.01 – $60.00 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Remove asphalt mat | square yard | 1,787 | — | $15.00 | $0.2 – $317.33 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Field office (class 2) | each | 1,759 | $17,265 | $37,000 | $1.00 – $337,269 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Mulching tackifier | pound | 1,743 | $3.00 | $10.43 | $0.01 – $530.00 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Delineator (type i) | each | 1,605 | $19.00 | $40.00 | $2.00 – $315.00 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Sign panel (class ii) | square foot | 1,582 | $22.00 | $26.00 | $1.18 – $158.00 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Gdrail type 3 (6-3) | linear foot | 1,576 | $16.00 | $32.10 | $6.06 – $165.00 | May 7, 2026, CDOT cost lookup · contract C27298 ↗ |
| Drum Channel DEV (Light) (F) | each | 1,570 | $51.00 | $8.00 | $1.00 – $2,000 | Sep 17, 2026, CDOT cost lookup · contract C26823 ↗ |
| Remove and disposal of sediment (labor) | hour | 1,553 | $50.00 | $60.00 | $0.01 – $470.00 | Oct 8, 2026, CDOT cost lookup · contract C26435R ↗ |
| RES Ground Sign | each | 1,548 | $195.00 | $450.00 | $12.80 – $6,000 | Oct 8, 2026, CDOT cost lookup · contract C24946 ↗ |
| Remove delineator | each | 1,544 | $7.00 | $10.00 | $0.9 – $500.00 | Sep 17, 2026, CDOT cost lookup · contract C26823 ↗ |
| Remove gdrail type 3 | linear foot | 1,460 | $3.35 | $7.00 | $0.75 – $142.73 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Concrete washout str | each | 1,459 | $851.32 | $5,000 | $0.1 – $81,929 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Hot mix asphalt (patch) (asphalt) | ton | 1,422 | $184.19 | $200.00 | $10.00 – $4,000 | Oct 8, 2026, CDOT cost lookup · contract C24946 ↗ |
| Erosion Log Type 1 (12 in) | linear foot | 1,419 | $5.02 | $20.00 | $0.01 – $533.50 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Delineator (type iii) | each | 1,365 | $22.55 | $40.00 | $4.50 – $420.00 | Oct 9, 2026, CDOT cost lookup · contract C27751 ↗ |
| Construction traffic sign (spec) | square foot | 1,352 | $19.00 | $48.00 | $1.00 – $320.00 | Oct 2, 2026, CDOT cost lookup · contract C27827 ↗ |
| Remove and disposal of sediment (equip) | hour | 1,324 | $105.00 | $120.00 | $0.01 – $841.52 | Oct 1, 2026, CDOT cost lookup · contract C26361R ↗ |